The business is going to establish a new office location. The information of the main jobs involved is provided in the table below. To finish this project as soon as possible, they also work on weekends (i.e., 7 days a week). Note that one-day job time means a full processing day through the midnight to next day. For example, if the job starts at 2/1/2023 and requires the job time of 3 days, it will be finished on 2/4/2023. Answer the questions below, Q1-Q3. Job A B С D E F G Description Lease the site Hire the workers Arrange for the furnishir Install the furnishings Arrange for the phones Install the phones Move into the office Immediate Predecessor A A C A D, E B,D,F Job Time 7 30 6 13 8 7 15 Q1: The business plans to start the project no sooner than 3/1/2023. The manager was told that it might take extra 3 days (i.e., a job time of 18 days instead of 15) to move into the office (Job G) because more equipment need to be relocated. It is possible that the installation of the furnishings (Job D) cannot start until 3/17/2023 due to the installation team's busy schedule in March. It is also possible that the phones cannot be arranged (job E) until 3/20/2023 given the cable/wiring issues recently found for repair. If with all these delays and issues for jobs D, E and G, what is the earliest date the project can be finished on? Besides the answer, you must show your calculation and analysis.
The business is going to establish a new office location. The information of the main jobs involved is provided in the table below. To finish this project as soon as possible, they also work on weekends (i.e., 7 days a week). Note that one-day job time means a full processing day through the midnight to next day. For example, if the job starts at 2/1/2023 and requires the job time of 3 days, it will be finished on 2/4/2023. Answer the questions below, Q1-Q3. Job A B С D E F G Description Lease the site Hire the workers Arrange for the furnishir Install the furnishings Arrange for the phones Install the phones Move into the office Immediate Predecessor A A C A D, E B,D,F Job Time 7 30 6 13 8 7 15 Q1: The business plans to start the project no sooner than 3/1/2023. The manager was told that it might take extra 3 days (i.e., a job time of 18 days instead of 15) to move into the office (Job G) because more equipment need to be relocated. It is possible that the installation of the furnishings (Job D) cannot start until 3/17/2023 due to the installation team's busy schedule in March. It is also possible that the phones cannot be arranged (job E) until 3/20/2023 given the cable/wiring issues recently found for repair. If with all these delays and issues for jobs D, E and G, what is the earliest date the project can be finished on? Besides the answer, you must show your calculation and analysis.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please Solve in Excel. ..
(Need all three questions. ...attempt if you will solve all three questions. ...thanks)
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Step 1: Examine - Given details:
VIEWStep 2: Q1) Calculate - Actual Duration:
VIEWSolution
VIEWStep 3: Q1) Calculate - Actual Duration - Date:
VIEWStep 4: Q1) Calculate - Actual Duration with delay:
VIEWStep 5: Q2) Calculate - Duration and Variance:
VIEWStep 6: Q2) Calculate - Duration and Path:
VIEWStep 7: Q2) Calculate - Probability:
VIEWStep 8: Q3) Calculate - Option 1 - Duration:
VIEWStep 9: Q3) Calculate - Option 1 - Probability:
VIEWStep 10: Q3) Calculate - Option 2 - Duration:
VIEWTrending now
This is a popular solution!
Step by step
Solved in 11 steps with 17 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.