The activities, duration, and cost under normal and accelerated crashed conditions for a network diagram are shown in the accompanying tabl Duration, days Cost, pesos Activity Node Accelerated Normal Accelerated A 1 to 2 2 6800 7200 8 2 to 3 24200 26800 C 2 to 4 4 8000 8000 4 to 3 3 6000 6900 3 to 5 2 5800 5800 5 to 6 4 7200 7550 3 to 7 3 8400 9000 7 10 6 1 4500 5200 6 to 8 5 9300 9700 3 to 9 5 5300 5900 9 to 10 7 29100 32100 8 to 10 1 1200 1200 10 to 11 2 8700 9000 D E F H I J K L M Normal 3 8 6 2 5 2 7 10 1 3
The activities, duration, and cost under normal and accelerated (crashed) conditions for a network diagram are shown in the accompanying table.
1. Determine the critical path of the project under normal conditions
2. Determine the duration of the project under normal conditions
3. Determine the cost of the project under normal conditions
4. Determine the minimum duration of the project
5. Determine the cost of the project when the duration is minimum?
Notes on answering:
For answering critical path, answer in capital letters only without hyphens,dashes,commas, or any symbols (i.e., ABJKM, AFLKO)
For answering durations and costs, answer in numerical value only without units. (i.e., for durations: 16, 12, 15. for costs: 12000,1500,17500)
Not following instructions in answering will not be considered
Step by step
Solved in 2 steps with 2 images