sieve analysis solve the ampty box and draw the chart and find d10.d30.d60
Wt.,
retained (g)
Cumulative
opening
(mm)
cumulative
%retained
sieve #
retained
Passing
Percent (%)
3/8
9.5
4.75
100
# 4
190
1394
198
#8
2.36
2.00
# 10
#30
0.595
0.425
70
# 40
27
28
N50
0.300
# 160
#200
0.15
0.075
21
11
pan
pan
Total
1944
Sieve Analysis
Chart:
D60
Cu=
D10
D10=
D30=
2
D30
Cz.c=D60+D10
D60=
Discussion:
1- We lost 1% of soil sample.
2- Most of sample in sieve # (.
3-
, ..... ....)
4-
5-
Transcribed Image Text:Wt., retained (g) Cumulative opening (mm) cumulative %retained sieve # retained Passing Percent (%) 3/8 9.5 4.75 100 # 4 190 1394 198 #8 2.36 2.00 # 10 #30 0.595 0.425 70 # 40 27 28 N50 0.300 # 160 #200 0.15 0.075 21 11 pan pan Total 1944 Sieve Analysis Chart: D60 Cu= D10 D10= D30= 2 D30 Cz.c=D60+D10 D60= Discussion: 1- We lost 1% of soil sample. 2- Most of sample in sieve # (. 3- , ..... ....) 4- 5-
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Experimental methods
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,