Shaw Incorporated began this period with a budget for 1,100 units of predicted production. The budgeted overhead at this predicted activity follows. At period-end, total actual overhead was $103,000, and actual units produced were 1,000. The company applies overhead with a standard of 3 DLH per unit and a standard overhead rate of $30 per DLH. Variable overhead Fixed overhead Total overhead $ 55,000 45,000 $ 100,000 a. Compute controllable variance. b. Compute volume variance. > Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Required A Required B Compute volume variance. Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Budgeted (flexible) overhead at units produced Standard overhead applied Volume variance Volume Variance ✓ $ 90,000 × 99,000 × $ 9,000 Unfavorable < Required A Required B < Shaw Incorporated began this period with a budget for 1,100 units of predicted production. The budgeted overhead at this predicted activity follows. At period-end, total actual overhead was $103,000, and actual units produced were 1,000. The company applies overhead with a standard of 3 DLH per unit and a standard overhead rate of $30 per DLH. Variable overhead Fixed overhead Total overhead $ 55,000 45,000 $ 100,000 a. Compute controllable variance. b. Compute volume variance. > Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Required A Required B Compute controllable variance. Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Controllable Variance Actual total overhead $ 103,000 Budgeted (flexible) overhead at units produced 90,000 × Controllable variance $ 13,000 Unfavorable < Required A Required B >

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter4: Job Order Costing
Section: Chapter Questions
Problem 7EA: A company estimates its manufacturing overhead will be $750,000 for the next year. What is the...
icon
Related questions
Question

Please do these two for me!!!!!!!

Shaw Incorporated began this period with a budget for 1,100 units of predicted production. The budgeted overhead at this predicted
activity follows. At period-end, total actual overhead was $103,000, and actual units produced were 1,000. The company applies
overhead with a standard of 3 DLH per unit and a standard overhead rate of $30 per DLH.
Variable overhead
Fixed overhead
Total overhead
$ 55,000
45,000
$ 100,000
a. Compute controllable variance.
b. Compute volume variance.
> Answer is complete but not entirely correct.
Complete this question by entering your answers in the tabs below.
Required A
Required B
Compute volume variance.
Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance.
Budgeted (flexible) overhead at units produced
Standard overhead applied
Volume variance
Volume Variance
✓ $
90,000 ×
99,000 ×
$
9,000 Unfavorable
< Required A
Required B
<
Transcribed Image Text:Shaw Incorporated began this period with a budget for 1,100 units of predicted production. The budgeted overhead at this predicted activity follows. At period-end, total actual overhead was $103,000, and actual units produced were 1,000. The company applies overhead with a standard of 3 DLH per unit and a standard overhead rate of $30 per DLH. Variable overhead Fixed overhead Total overhead $ 55,000 45,000 $ 100,000 a. Compute controllable variance. b. Compute volume variance. > Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Required A Required B Compute volume variance. Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Budgeted (flexible) overhead at units produced Standard overhead applied Volume variance Volume Variance ✓ $ 90,000 × 99,000 × $ 9,000 Unfavorable < Required A Required B <
Shaw Incorporated began this period with a budget for 1,100 units of predicted production. The budgeted overhead at this predicted
activity follows. At period-end, total actual overhead was $103,000, and actual units produced were 1,000. The company applies
overhead with a standard of 3 DLH per unit and a standard overhead rate of $30 per DLH.
Variable overhead
Fixed overhead
Total overhead
$ 55,000
45,000
$ 100,000
a. Compute controllable variance.
b. Compute volume variance.
> Answer is complete but not entirely correct.
Complete this question by entering your answers in the tabs below.
Required A Required B
Compute controllable variance.
Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance.
Controllable Variance
Actual total overhead
$
103,000
Budgeted (flexible) overhead at units produced
90,000 ×
Controllable variance
$
13,000 Unfavorable
< Required A
Required B >
Transcribed Image Text:Shaw Incorporated began this period with a budget for 1,100 units of predicted production. The budgeted overhead at this predicted activity follows. At period-end, total actual overhead was $103,000, and actual units produced were 1,000. The company applies overhead with a standard of 3 DLH per unit and a standard overhead rate of $30 per DLH. Variable overhead Fixed overhead Total overhead $ 55,000 45,000 $ 100,000 a. Compute controllable variance. b. Compute volume variance. > Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Required A Required B Compute controllable variance. Note: Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Controllable Variance Actual total overhead $ 103,000 Budgeted (flexible) overhead at units produced 90,000 × Controllable variance $ 13,000 Unfavorable < Required A Required B >
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning