Sahara Industries has established the following labor standards for one of its products: Standard hours per unit of output 6.0 hours Standard variable overhead rate $20.00 per hour The following data relate to last month's operations: Actual hours 10,500 hours 1,700 units Actual total variable overhead cost $210,000 Actual output What is the variable overhead efficiency variance for the month?

icon
Related questions
Question
100%

What is the variable overhead efficiency variance for the month ?

Sahara Industries has established the following labor
standards for one of its products:
Standard hours per unit of output 6.0 hours
Standard variable overhead rate $20.00 per hour
The following data relate to last month's operations:
Actual hours
10,500 hours
1,700 units
Actual total variable overhead cost $210,000
Actual output
What is the variable overhead efficiency variance for the
month?
Transcribed Image Text:Sahara Industries has established the following labor standards for one of its products: Standard hours per unit of output 6.0 hours Standard variable overhead rate $20.00 per hour The following data relate to last month's operations: Actual hours 10,500 hours 1,700 units Actual total variable overhead cost $210,000 Actual output What is the variable overhead efficiency variance for the month?
Expert Solution
steps

Step by step

Solved in 2 steps