Q5) Assume that 2 automatic machines have been assigned to one operator. It takes 2 minute to load a machine, 2 minute to unload a machine, 5 minutes of automatic machine time, and 2 minute to inspect and pack a finished part. Draw machine operator chart and determine the amount of idleness that happens to either operator or machines as well as cycle time.
Q5) Assume that 2 automatic machines have been assigned to one operator. It takes 2 minute to load a machine, 2 minute to unload a machine, 5 minutes of automatic machine time, and 2 minute to inspect and pack a finished part. Draw machine operator chart and determine the amount of idleness that happens to either operator or machines as well as cycle time.
Precision Machining Technology (MindTap Course List)
2nd Edition
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Chapter8: Computer Numerical Control
Section8.4: Cnc Turning: Setup And Operation
Problem 4RQ: What is the process called where a program is sent to a machine one block at a time as the machine...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Precision Machining Technology (MindTap Course Li…
Mechanical Engineering
ISBN:
9781285444543
Author:
Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:
Cengage Learning
Precision Machining Technology (MindTap Course Li…
Mechanical Engineering
ISBN:
9781285444543
Author:
Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:
Cengage Learning