Product Machine hours to produce one lot Demand in liters Chavo Milk 100 400,000 Choco-chavo Milk 150 100,000 Chavo Milk Light 130 180,000
The Lechería La Vaquita company currently has three-star products, but it faces a problem of capacity to satisfy the demand for these products. In total, it has 65,000 machine hours per month for the production of these three products. The production time to produce a batch of 1000 liters each product, as well as its monthly demands are shown in the following table:
* TABLE *
Because in recent months there have been advertising campaigns for Leche Choco-Chavo and Leche Chavo Light, the company wants the demands for these products to be the first to be satisfied with the same level of importance, while Leche Chavo as it is a product already well positioned, it is the third priority of these products.
Formulate the goal programming mathematical model for this problem by clearly defining the sets, constraint variables, parameters, objective function (s), and constraints.