Problem 9-10 (Algo) In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. Note: Leave the cells blank, whenever zero (0) is required. ITEM J Gross requirements On-hand Net requirements Planned-order receipt Planned-order release WEEK NUMBER 0 1 2 3 4 73 5 55 74 43 Period 1 2 3 4 5 73 55 74 Item: J OH: 43 LT: 1 SS: 0 Q: L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases

Intermediate Algebra
19th Edition
ISBN:9780998625720
Author:Lynn Marecek
Publisher:Lynn Marecek
Chapter12: Sequences, Series And Binomial Theorem
Section12.3: Geometric Sequences And Series
Problem 12.58TI: What is the total effect on the economy of a government tax rebate of $500 to each household in...
icon
Related questions
Question

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week.

Note: Leave the cells blank, whenever zero (0) is required.

ITEM J WEEK NUMBER
0 1 2 3 4 5
Gross requirements     73   55 74
On-hand 43          
Net requirements            
Planned-order receipt            
Planned-order release
Problem 9-10 (Algo)
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and
planned-order releases to meet the gross requirements. Lead time is one week.
Note: Leave the cells blank, whenever zero (0) is required.
ITEM J
Gross requirements
On-hand
Net requirements
Planned-order receipt
Planned-order release
WEEK NUMBER
0
1
2 3 4
73
5
55
74
43
Period
1
2
3
4
5
73
55
74
Item: J
OH: 43
LT: 1
SS: 0
Q: L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Transcribed Image Text:Problem 9-10 (Algo) In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week. Note: Leave the cells blank, whenever zero (0) is required. ITEM J Gross requirements On-hand Net requirements Planned-order receipt Planned-order release WEEK NUMBER 0 1 2 3 4 73 5 55 74 43 Period 1 2 3 4 5 73 55 74 Item: J OH: 43 LT: 1 SS: 0 Q: L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Algebra
Intermediate Algebra
Algebra
ISBN:
9780998625720
Author:
Lynn Marecek
Publisher:
OpenStax College