Problem 2- Use the information below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point. Fill out and calculate the table with your direct cost results. Graph your results for direct cost, indirect cost, total cost, and with incentive cost Sc A ACT. NORMAL NORMAL MAXIMUM CRASH TIME COST CRASH COST TIME (slope) B A B A 10 40 2 80 B 8 10 3 30 с 5 80 1 40 с E D 11 50 2 50 E 15 100 4 100 F 6 20 1 30 300 A D 10 11 27 PROJECT DURATION B B 8 F 6 TOTAL DIRECT COST C E CP= 5 15 B A D C E PROJECT DURATION TOTAL DIRECT COST F ACTIVITIES CHANGED D с E A 26 B E F 25 PROJECT DURATION TOTAL DIRECT COST ACTIVITIES CHANGED CP- 24 PROJECT DURATION F TOTAL DIRECT COST ACTIVITIES CHANGED CP= PROJECT DURATION TOTAL DIRECT COST ACTIVITIES CHANGED CP- 23 Exac d 22 PROJECT DURATION PROJECT DURATION 22 DIRECT COSTS INDIRECT COSTS TOTAL WITH COSTS INCENTIVE 50 23 60 TOTAL DIRECT 24 120 COST 25 180 ACTIVITIES CHANGED 26 240 27 300 | | | | | | с E 1000 CP = 800 600 PROJECT DURATION lincentive 22 23 24 25 26 27 -60 -40 -30 -20 -10 0 400 200 22 23 24 25 26 27
Problem 2- Use the information below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point. Fill out and calculate the table with your direct cost results. Graph your results for direct cost, indirect cost, total cost, and with incentive cost Sc A ACT. NORMAL NORMAL MAXIMUM CRASH TIME COST CRASH COST TIME (slope) B A B A 10 40 2 80 B 8 10 3 30 с 5 80 1 40 с E D 11 50 2 50 E 15 100 4 100 F 6 20 1 30 300 A D 10 11 27 PROJECT DURATION B B 8 F 6 TOTAL DIRECT COST C E CP= 5 15 B A D C E PROJECT DURATION TOTAL DIRECT COST F ACTIVITIES CHANGED D с E A 26 B E F 25 PROJECT DURATION TOTAL DIRECT COST ACTIVITIES CHANGED CP- 24 PROJECT DURATION F TOTAL DIRECT COST ACTIVITIES CHANGED CP= PROJECT DURATION TOTAL DIRECT COST ACTIVITIES CHANGED CP- 23 Exac d 22 PROJECT DURATION PROJECT DURATION 22 DIRECT COSTS INDIRECT COSTS TOTAL WITH COSTS INCENTIVE 50 23 60 TOTAL DIRECT 24 120 COST 25 180 ACTIVITIES CHANGED 26 240 27 300 | | | | | | с E 1000 CP = 800 600 PROJECT DURATION lincentive 22 23 24 25 26 27 -60 -40 -30 -20 -10 0 400 200 22 23 24 25 26 27
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 30P
Related questions
Question
FIll out the charts
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 9 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,