Problem 2 (2 points) 2.1 A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation costs 2.6 million dollars and the annual maintenance cost is $26,000. Every 11 years, the system needs to be fully examined which requires a fixed management and material cost of $30,000 and a variable labor cost at the rate of $30/hr. 18 full time (working 8 hours per day) workers will be employed for 60 days for this task. If the infrastructure has a life time of 132 years and the city's interest rate is 4%, (Please round your answer to two decimal places at the million level for both questions, e.g. '1.23' millions) a. what is the capitalized worth of the project (in millions)? Please note that the value could be negative. (1 point) $ 1.48 Incorrect (0 points) Show Your Attempts v 2.2 b) what is the EUAC of the infrastructure (in million dollars)? $ LATEX You have used 2 of 5 attempts Submitted Mar 3, 3:37 PM Submit (1 point) LATEX
Problem 2 (2 points) 2.1 A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation costs 2.6 million dollars and the annual maintenance cost is $26,000. Every 11 years, the system needs to be fully examined which requires a fixed management and material cost of $30,000 and a variable labor cost at the rate of $30/hr. 18 full time (working 8 hours per day) workers will be employed for 60 days for this task. If the infrastructure has a life time of 132 years and the city's interest rate is 4%, (Please round your answer to two decimal places at the million level for both questions, e.g. '1.23' millions) a. what is the capitalized worth of the project (in millions)? Please note that the value could be negative. (1 point) $ 1.48 Incorrect (0 points) Show Your Attempts v 2.2 b) what is the EUAC of the infrastructure (in million dollars)? $ LATEX You have used 2 of 5 attempts Submitted Mar 3, 3:37 PM Submit (1 point) LATEX
Chapter4: Economic Evaluation In Health Care
Section: Chapter Questions
Problem 7QAP
Related questions
Question
Not use ai

Transcribed Image Text:Problem 2
(2 points)
2.1 A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation
costs 2.6 million dollars and the annual maintenance cost is $26,000. Every 11 years, the system needs to be
fully examined which requires a fixed management and material cost of $30,000 and a variable labor cost at the
rate of $30/hr. 18 full time (working 8 hours per day) workers will be employed for 60 days for this task. If the
infrastructure has a life time of 132 years and the city's interest rate is 4%,
(Please round your answer to two decimal places at the million level for both questions, e.g. '1.23'
millions)
a. what is the capitalized worth of the project (in millions)? Please note that the value could be negative.
(1 point)
$
1.48
Incorrect (0 points)
Show Your Attempts v
2.2 b) what is the EUAC of the infrastructure (in million dollars)?
$
LATEX
You have used 2 of 5 attempts
Submitted Mar 3, 3:37 PM
Submit
(1 point)
LATEX
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you


Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning

Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning


Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning

Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning



Economics (MindTap Course List)
Economics
ISBN:
9781337617383
Author:
Roger A. Arnold
Publisher:
Cengage Learning