Peter’s Paper Clips uses a three-stage production process: cutting wire to prescribed lengths, inner bending, and outer bending. The cutting process can produce at a rate of 220 pieces per minute; inner bending, 230 pieces per minute; and outer bending, 180 pieces per minute. Determine the hourly capacity of each process stage and the number of machines needed to meet an output rate of 14,000 units per hour. Round your answers for the hourly capacity of each process stage to the nearest whole mumber. Round your answers up for the number of machines needed to a whole number. Cutting process: Hourly capacity: pieces/hour Number of machines needed: machine(s) Inner bending: Hourly capacity: pieces/hour Number of machines needed: machine(s) Outer bending: Hourly capacity: pieces/hour Number of machines needed: machine(s)
Peter’s Paper Clips uses a three-stage production process: cutting wire to prescribed lengths, inner bending, and outer bending. The cutting process can produce at a rate of 220 pieces per minute; inner bending, 230 pieces per minute; and outer bending, 180 pieces per minute. Determine the hourly capacity of each process stage and the number of machines needed to meet an output rate of 14,000 units per hour. Round your answers for the hourly capacity of each process stage to the nearest whole mumber. Round your answers up for the number of machines needed to a whole number.
Cutting process:
Hourly capacity: pieces/hour
Number of machines needed: machine(s)
Inner bending:
Hourly capacity: pieces/hour
Number of machines needed: machine(s)
Outer bending:
Hourly capacity: pieces/hour
Number of machines needed: machine(s)
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images