Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. ES SL LS ID EF Time SL Activity A B C LF DEF D GH 6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation I J K L Predecessor A, B C E F E D D, G, I I H Duration in Weeks 5 3 8 3 4 10 8 18 20 7 5 10

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new
football stadium. He developed the activities, durations, and predecessor relationships in the
following table for delivering company valuations.
Activity
A
B
C
D
E
F
G
H
1
J
K
L
ES
ID
EF
¤¯¯
SL
SL
LS
Time LF
Predecessor
A, B
C
E
F
E
D
D, G, I
1
Duration in Weeks
5
3
8
3
4
10
8
18
20
7
5
10
6A. Draw the Network Diagram, and identify and discuss the project duration and the
critical path using the following activity notation
Transcribed Image Text:Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity A B C D E F G H 1 J K L ES ID EF ¤¯¯ SL SL LS Time LF Predecessor A, B C E F E D D, G, I 1 Duration in Weeks 5 3 8 3 4 10 8 18 20 7 5 10 6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

b) Draw the project’s Gantt chart 

 

c) Change the time of at least two activities that can reduce the overall project duration, draw the new critical path and the new Gantt chart 

Solution
Bartleby Expert
SEE SOLUTION
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.