Max 200DRB + 280DRW 20DRB + 25DRW < 40,000 Steel available 40DRB + 100DRW 120,000 Manufacturing minutes 60DRB + 40DRW < 96,000 Assembly minutes BRB, DRW > 0 What are the optimal solution and the total profit contribution? Another supplier offered to provide Deegan Industries with an additional 500 pounds of the steel alloy at $2 per pound. Should Deegan purchase the additional pounds of the steel alloy? Explain. Deegan is considering using overtime to increase the available assembly time. What would you advise Deegan to do regarding this option? Explain. Because of increased competition, Deegan is considering reducing the price of model DRB such

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question

UNIT 5 CHAPTER 8

  1. The Porsche Club of America sponsors driver education events that provide high-performance driving instruction on actual racetracks. Because safety is a primary consideration at such events, many owners elect to install roll bars in their cars. Deegan Industries manufactures two types of roll bars for Porsches. Model DRB is bolted to the car using existing holes in the car's frame. Model DRW is a heavier roll bar that must be welded to the car's frame. Model DRB requires 20 pounds of a special high-alloy steel, 40 minutes of manufacturing time, and 60 minutes of assembly time. Model DRW requires 25 pounds of the special high-alloy steel, 100 minutes of manufacturing time, and 40 minutes of assembly time. Deegan's steel supplier indicated that at most 40,000 pounds of the high-alloy steel will be available next quarter. In addition, Deegan estimates that 2000 hours of manufacturing time and 1600 hours of assembly time will be available next quarter. The profit contributions are $200 per unit for model DRB and $280 per unit for model DRW. The linear programming model for this problem is as follows: 

Max 200DRB + 280DRW

20DRB + 25DRW < 40,000 Steel available

40DRB + 100DRW 120,000 Manufacturing minutes

60DRB + 40DRW < 96,000 Assembly minutes

BRB, DRW > 0

  1. What are the optimal solution and the total profit contribution?
  2. Another supplier offered to provide Deegan Industries with an additional 500 pounds of the steel alloy at $2 per pound. Should Deegan purchase the additional pounds of the steel alloy? Explain.
  3. Deegan is considering using overtime to increase the available assembly time. What would you advise Deegan to do regarding this option? Explain.
  4. Because of increased competition, Deegan is considering reducing the price of model DRB such that the new contribution to profit is $175 per unit. How would this change in price affect the optimal solution? Explain.
  5. If the available manufacturing time is increased by 500 hours, will the shadow price for the manufacturing time constraint change? Explain.

Variable Cells

Model Variable

Name

Final Value

Reduced Cost

DRB

MODEL DRB

1000.000

0.000

DRW

MODEL DRW

800.000

0.000

 

Constraints

Constraints number

Name

Final Value

Shadow price

DRB

MODEL DRB

1000.000

0.000

Variable Cells

Model Variable

Name

Final Value

Reduced Cost

1

Steel available

40000.000

8.800

2

Manufacturing minutes

120000.000

0.600

3

Assembly minutes

92000.000

0.000

 

 

 

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,