Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: Task a Time (min. .2 .2 .4 .1 .3 .2 .1 .2 Immediate Predecessor none a none none c, d be none £ g (A) Determine the maximum and minimum cycle time. (B) Determine the optimum cycle time. (C) What is the minimum number of stations needed?

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question

Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below:

Task

a

Time (min.

.2

.2

.4

.1

.3

.2

.1

.2

Immediate Predecessor

none

a

none

none

c, d be

none

£ g

(A) Determine the maximum and minimum cycle time.

(B) Determine the optimum cycle time.

(C) What is the minimum number of stations needed?

(D) Draw the precedence diagram.

(E) Assign tasks to stations in order of most following tasks first.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Process selection
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing