15.26. The Best Wheels Bicycle Company has scheduled the produc- tion of the following bicycles this month: Week Model 1 2 3 4 [B2610] 26-inch 10-speed 50 100 195 150 [B2003] 20-inch 3-speed 15 30 65 45 [B2001] 20-inch 1-speed 20 40 80 60 The two critical work centers for producing these bikes are welding and assembly. Welding has an efficiency of 95% and a utilization of 90%. Assembly has an efficiency of 90% and a utilization of 92%. The time required (in hours) by each bike in the two work centers is as follows: Welding Assembly B2610 0.20 0.18 B2003 0.15 0.15 B2001 0.07 0.10

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Assume 40 hours are available per week for each work center. Calcu- late the capacity and load percent per work center per week.
15.26. The Best Wheels Bicycle Company has scheduled the produc-
tion of the following bicycles this month:
Week
Model
1
2
3
4
[B2610]
26-inch 10-speed
50
100
195
150
[B2003]
20-inch 3-speed
15
30
65
45
[B2001]
20-inch 1-speed
20
40
80
60
The two critical work centers for producing these bikes are welding and
assembly. Welding has an efficiency of 95% and a utilization of 90%.
Assembly has an efficiency of 90% and a utilization of 92%. The time
required (in hours) by each bike in the two work centers is as follows:
Welding
Assembly
B2610
0.20
0.18
B2003
0.15
0.15
B2001
0.07
0.10
Transcribed Image Text:15.26. The Best Wheels Bicycle Company has scheduled the produc- tion of the following bicycles this month: Week Model 1 2 3 4 [B2610] 26-inch 10-speed 50 100 195 150 [B2003] 20-inch 3-speed 15 30 65 45 [B2001] 20-inch 1-speed 20 40 80 60 The two critical work centers for producing these bikes are welding and assembly. Welding has an efficiency of 95% and a utilization of 90%. Assembly has an efficiency of 90% and a utilization of 92%. The time required (in hours) by each bike in the two work centers is as follows: Welding Assembly B2610 0.20 0.18 B2003 0.15 0.15 B2001 0.07 0.10
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.