Learning Curves 1. Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 54 hours to complete. a) What is the learning rate? b) What is the estimated time for the 40th unit? c) What is the estimated total time for producing all 40 units? d) What is the average time per unit for producing the last 10 units (#30 - #40)?
Learning
1. Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 54 hours to complete.
a) What is the learning rate?
b) What is the estimated time for the 40th unit?
c) What is the estimated total time for producing all 40 units?
d) What is the average time per unit for producing the last 10 units (#30 - #40)?
Note: - Since we can answer only up to 3 subparts we will answer only the first three subparts(a, b, and c) for your question. Please resubmit the question by specifying the remaining subparts that have to be answered.
Given data is
Total units = 40
Time required by first unit = 60 hrs
Time required by second unit = 54 hrs