Suppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions: If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 it takes hours For x = 3 it takes hours
Suppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions:
-
If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place.
For x = 2 it takes hours
For x = 3 it takes hours
-
If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place.
For x = 2 and a 65% LC, it takes hours
For x = 3 and a 65% LC, it takes hours
For x = 2 and a 95% LC, it takes hours
For x = 3 and a 95% LC, it takes hours
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 6 images