II. In a basketball game at the Arena, Pasay City, the booth opened at 4pm, and vehicles began to arrive at a rate of 2400 vph for 25 minutes and then changes to 600 vph. The fee booth attendant spends 3 seconds with each car. Determine the following: 4)Longest queue. a) 400 veh b) 290 veh c) 500 veh d) 530 veh 5)Time when queue dissipates. a) 55:10 pm b) 5:15 pm c) 4:48 pm 6)Queue of vehicles at 4:42pm. a) 330 veh b) 380 veh c) 275 veh d) 6:02 pm d) 305 veh

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter2: Transportation Systems And Organizations
Section: Chapter Questions
Problem 4P
icon
Related questions
Question
II. In a basketball game at the Arena, Pasay City, the booth opened at 4pm, and
vehicles began to arrive at a rate of 2400 vph for 25 minutes and then changes
to 600 vph. The fee booth attendant spends 3 seconds with each car. Determine
the following:
4)Longest queue.
a) 400 veh
b) 290 veh
c) 500 veh
d) 530 veh
5)Time when queue dissipates.
a) 55:10 pm
b) 5:15 pm
c) 4:48 pm
6)Queue of vehicles at 4:42pm.
a) 330 veh
b) 380 veh
c) 275 veh
7) At what time did the 1,110th vehicle entered the queue.
a) 5:12 pm
b) 43:26 pm
c) 4:36 pm
8) How much time that the 1,110 vehicle spent in the queue.
a) 13.5min
c) 22.75min
b) 20.25 min
9)Total vehicle delay in vehicle-hour.
a) 38.15 ve.hr b) 362.25 veh. hr
c) 375.75veh.hr d) 312.5 veh.hr
d) 6:02 pm
d) 305 veh
d) 4:54 pm
d)24.50min
Transcribed Image Text:II. In a basketball game at the Arena, Pasay City, the booth opened at 4pm, and vehicles began to arrive at a rate of 2400 vph for 25 minutes and then changes to 600 vph. The fee booth attendant spends 3 seconds with each car. Determine the following: 4)Longest queue. a) 400 veh b) 290 veh c) 500 veh d) 530 veh 5)Time when queue dissipates. a) 55:10 pm b) 5:15 pm c) 4:48 pm 6)Queue of vehicles at 4:42pm. a) 330 veh b) 380 veh c) 275 veh 7) At what time did the 1,110th vehicle entered the queue. a) 5:12 pm b) 43:26 pm c) 4:36 pm 8) How much time that the 1,110 vehicle spent in the queue. a) 13.5min c) 22.75min b) 20.25 min 9)Total vehicle delay in vehicle-hour. a) 38.15 ve.hr b) 362.25 veh. hr c) 375.75veh.hr d) 312.5 veh.hr d) 6:02 pm d) 305 veh d) 4:54 pm d)24.50min
Expert Solution
steps

Step by step

Solved in 5 steps with 8 images

Blurred answer
Knowledge Booster
Beams
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning