If the athletic director plans to start the project on January 1, calculate the probability the track and field team will be ready by the scheduled April 1 date (13 weeks) based solely on the critical path. (Round your answer to four decimal places.)   Should the athletic director begin planning the track and field team before January 1? (The probability for finishing on schedule should be at least 0.9.) Since the probability that the track and field team will be ready by April 1 is      than 0.9, the athletic director      begin planning before January 1.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
I ONLY NEED HELP WITH PART. (D) Please and thank you. 
 
You may need to use the appropriate technology to answer this question.
Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table.
      Time (Weeks)
Activity Description Immediate
Predecessor
Optimistic Most Probable Pessimistic
A Meet with board   1 1 2
B Hire coaches A 4 6 8
C Conduct fundraiser A 2 4 6
D Announce program B, C 1 2 3
E Meet with coaches B 2 3 4
F Order team equipment A 1 2 3
G Register athletes D 1 2 3
H Reserve buses for meets G 1 2 3
I Plan first practice E, H, F 1 1 1
(a)
Draw a project network.
A project network with 11 activities and 13 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B, to activity C, and to activity F.
  • Activity B is connected to activity E.
  • Activity C is connected to activity D.
  • Activity D is connected to activity G.
  • Activity E is connected to activity G and to activity I.
  • Activity F is connected to activity I.
  • Activity G is connected to activity H.
  • Activity H is connected to activity I.
  • Activity I is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
 
A project network with 11 activities and 13 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B, to activity C, and to activity F.
  • Activity B is connected to activity D and to activity E.
  • Activity C is connected to activity D.
  • Activity D is connected to activity G.
  • Activity E is connected to activity I.
  • Activity F is connected to activity I.
  • Activity G is connected to activity H.
  • Activity H is connected to activity I.
  • Activity I is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
 
A project network with 11 activities and 14 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B, to activity C, and to activity F.
  • Activity B is connected to activity E.
  • Activity C is connected to activity D and to activity E.
  • Activity D is connected to activity G.
  • Activity E is connected to activity G and to activity I.
  • Activity F is connected to activity I.
  • Activity G is connected to activity H.
  • Activity H is connected to activity I.
  • Activity I is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
 
A project network with 11 activities and 13 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B, to activity C, and to activity F.
  • Activity B is connected to activity E.
  • Activity C is connected to activity D and to activity E.
  • Activity D is connected to activity G.
  • Activity E is connected to activity I.
  • Activity F is connected to activity I.
  • Activity G is connected to activity H.
  • Activity H is connected to activity I.
  • Activity I is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
(b)
Develop an activity schedule. (Round your answers to two decimal places.)
Activity Earliest
Start
Latest
Start
Earliest
Finish
Latest
Finish
Slack
A          
B          
C          
D          
E          
F          
G          
H          
I          
(c)
What are the critical activities? (Enter your answers as a comma-separated list.)
A,B,D,G,H,I
 
 
 
What is the expected project completion time (in weeks)? (Round your answer to two decimal places.)
  weeks
(d)
If the athletic director plans to start the project on January 1, calculate the probability the track and field team will be ready by the scheduled April 1 date (13 weeks) based solely on the critical path. (Round your answer to four decimal places.)
 
Should the athletic director begin planning the track and field team before January 1? (The probability for finishing on schedule should be at least 0.9.)
Since the probability that the track and field team will be ready by April 1 is      than 0.9, the athletic director      begin planning before January 1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Business reports
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.