Joe and Noël have just gotten engaged. Seeing as they are both business students, they thought that they’d try to plan out their wedding preparation as a project. Here’s the WBS they’ve determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, use the standard calendar in ProjectLibre (use default working days in software). Based on the project you created, answer the following questions. Please note that each question is independent and not built upon each other. a) If Joe and Noël start wedding planning on January 1, 2023, when is the wedding day? b) What is the critical path? List all critical tasks in chronological order. c) Will the critical path change if Noël decides she needs two extra weeks for the Bridal Diet? If yes, what is the new critical path and when should the wedding be held?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Joe and Noël have just gotten engaged. Seeing as they are both business students, they thought that they’d try to plan out their wedding preparation as a project. Here’s the WBS they’ve determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, use the standard calendar in ProjectLibre (use default working days in software).
Based on the project you created, answer the following questions. Please note that each question is independent and not built upon each other.
-
a) If Joe and Noël start wedding planning on January 1, 2023, when is the wedding day?
-
b) What is the critical path? List all critical tasks in chronological order.
-
c) Will the critical path change if Noël decides she needs two extra weeks for the Bridal Diet? If yes, what is the new critical path and when should the wedding be held?
-
d) Assume that band auditions take twice as long as expected. Does this affect the wedding day? If yes, when should the wedding be held?
-
e) If they want to get married on 10/1/2022, when do they have to start the wedding planning?
-
f) Determine what predecessors need to be listed to make sure everything is done by the wedding day without needlessly checking things? Noël is going to be nervous enough without having to check to see if each of the 18 tasks are complete at the end!