How many days would a 66-unit construction activity lasts if this activity have a parameter of 0.7manhours per unit would last and that there's only 9hrs per day allotted to construction work. Neglect any additional allowances for overtime. Note: Type your exact final answer without oloitting any decimals on the space provided.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
icon
Related questions
icon
Concept explainers
Question
How many days would a 66-unit construction activity lasts if this activity have a parameter of 0.7manhours per unit would last and that
there's only 9hrs per day allotted to construction work. Neglect any additional allowances for overtime.
Note: Type your exact final answer without olpitting any decimals on the space provided.
Transcribed Image Text:How many days would a 66-unit construction activity lasts if this activity have a parameter of 0.7manhours per unit would last and that there's only 9hrs per day allotted to construction work. Neglect any additional allowances for overtime. Note: Type your exact final answer without olpitting any decimals on the space provided.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Budget estimating
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,