Homework #1 For the shown project, answer the following questions (durations re in days). Optimistic Most likely Pesimistic duration ID Description 1 Start 2 Producers asociation organization 3 Historical features development 4 To hire expeditor 5 Twenty beneficiaries identification 6 Producers asociation formalization 7 Cultural features development 8 Technical norm proposal development 9 Technical norm proposal approval 10 Ten beneficiaries diagnosis 11 Techinical assistance to five beneficiaries 12 Joining of five entrepreneurs with exporters 13 Ten beneficiaries diagnosis 14 Techinical assistance to five beneficiaries 15 Joining of five entrepreneurs with exporters Predecesor duration NA duration 70 33 30 40 51 33 38 54 40 59 93 56 50 61 22 1 22 1 31 2 30 90 56 51 3 22 6,7 8 25 36 102 4,5 25 55 10 59 70 93 35 40 70 35 11 25 45 10 13 14 55 93 25 59 25 45 A. Construct a PERT chart for the project. B. Identify the critical path and hence the minimum time to completion. C. Describe where there is slack time in the system. D. Calculate the probability that the project ends at 200 days. E. Calculate the probability activity (11) finishes in less than 70 days F. Estimate project completion date with at least 90% confidence level G. Calculate the probability that activity (12) has a float > 35 days.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
100%
5:39 4
ll 68% É
HW_Due_to_22_5_20...
Нomework #1
For the shown project, answer the following questions (durations re in days).
Optimistic Most likely Pesimistic
duration
ID Description
1 Start
2 Producers asociation organization
3 Historical features development
4 To hire expeditor
5 Twenty beneficiaries identification
6 Producers asociation formalization
7 Cultural features development
8 Technical norm proposal development
9 Technical norm proposal approval
10 Ten beneficiaries diagnosis
11 Techinical assistance to five beneficiaries
12 Joining of five entrepreneurs with exporters
13 Ten beneficiaries diagnosis
14 Techinical assistance to five beneficiaries
15 Joining of five entrepreneurs with exporters
Predecesor duration
duration
NA
59
70
93
56
50
1
22
33
30
40
51
33
22
1
31
61
30
90
56
51
102
3
22
6,7
25
36
38
54
4,5
10
11
25
40
70
35
40
5
93
59
25
25
45
10
13
55
93
59
70
14
25
35
45
A. Construct a PERT chart for the project.
B. Identify the critical path and hence the minimum time to completion.
C. Describe where there is slack time in the system.
D. Calculate the probability that the project ends at 200 days.
E. Calculate the probability activity (11) finishes in less than 70 days
F. Estimate project completion date with at least 90% confidence level
G. Calculate the probability that activity (12) has a float > 35 days.
II
O
Transcribed Image Text:5:39 4 ll 68% É HW_Due_to_22_5_20... Нomework #1 For the shown project, answer the following questions (durations re in days). Optimistic Most likely Pesimistic duration ID Description 1 Start 2 Producers asociation organization 3 Historical features development 4 To hire expeditor 5 Twenty beneficiaries identification 6 Producers asociation formalization 7 Cultural features development 8 Technical norm proposal development 9 Technical norm proposal approval 10 Ten beneficiaries diagnosis 11 Techinical assistance to five beneficiaries 12 Joining of five entrepreneurs with exporters 13 Ten beneficiaries diagnosis 14 Techinical assistance to five beneficiaries 15 Joining of five entrepreneurs with exporters Predecesor duration duration NA 59 70 93 56 50 1 22 33 30 40 51 33 22 1 31 61 30 90 56 51 102 3 22 6,7 25 36 38 54 4,5 10 11 25 40 70 35 40 5 93 59 25 25 45 10 13 55 93 59 70 14 25 35 45 A. Construct a PERT chart for the project. B. Identify the critical path and hence the minimum time to completion. C. Describe where there is slack time in the system. D. Calculate the probability that the project ends at 200 days. E. Calculate the probability activity (11) finishes in less than 70 days F. Estimate project completion date with at least 90% confidence level G. Calculate the probability that activity (12) has a float > 35 days. II O
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Work breakdown structure
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning