Question 1: A project consist of the following activities the duration and relationships between activities are given in table. a- Draw the network diagram. b- Determine total duration c- Determine critical path d- Determine total float for activity (G, H, D) e- Determine (Z) at Ts =55 f- Determine probability at Ts = 58 Activity optimistic Most pessimistic ТЕ predecessor likely E 10 15 10 None D 4 7 10 7 E R 4 7 10 7 E F 4 7 10 7 E C 8 13 8 K 4 8. 12 8. 2 8 14 8 R,F J 2 10 12 9 C В 6. 8 22 10 J A 10 20 11 I 6. 11 16 11 H 5 10 15 10 2 10 12 9. K.C M 4 9. 14 9. L 10 15 10 M N 6. 10 20 11 Q

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

Please hurry to send the answer

 

Question 1: A project consist of the following activities the duration and relationships between
activities are given in table.
a- Draw the network diagram.
b- Determine total duration
c- Determine critical path
d- Determine total float for activity (G, H, D)
e- Determine (Z) at Ts =55
f- Determine probability at Ts = 58
Activity
optimistic
Most
pessimistic
ТЕ
predecessor
likely
E
5
10
15
10
None
D
4
7
10
7
E
R
4
7
10
7
E
F
4
7
10
7
E
C
3
13
8
D
K
4
8
12
8
R
2
8
14
8
R,F
J
10
12
9.
C
В
8
22
10
J
A
6.
10
20
11
I
11
16
11
H
H
10
15
10
G
10
12
9
K.C
M
9
14
9
L
Q
10
15
10
M
N
10
20
11
Q
652456
Transcribed Image Text:Question 1: A project consist of the following activities the duration and relationships between activities are given in table. a- Draw the network diagram. b- Determine total duration c- Determine critical path d- Determine total float for activity (G, H, D) e- Determine (Z) at Ts =55 f- Determine probability at Ts = 58 Activity optimistic Most pessimistic ТЕ predecessor likely E 5 10 15 10 None D 4 7 10 7 E R 4 7 10 7 E F 4 7 10 7 E C 3 13 8 D K 4 8 12 8 R 2 8 14 8 R,F J 10 12 9. C В 8 22 10 J A 6. 10 20 11 I 11 16 11 H H 10 15 10 G 10 12 9 K.C M 9 14 9 L Q 10 15 10 M N 10 20 11 Q 652456
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning