Q4: Consider the following table summarizing the details of a project Activity Predecessor(s) Duration (weeks) Most likely time Pessimistic time 8. Optimistic time A 3 6. 9. 4. 4. 5. 6. 3 3. 9. 4. 11 8. C,D C,D.E F 9. 6. H 3. 9. (a) Construct the project network. (b) Find the expected duration and variance of each activity. (c) Find the critical path and the expected projeet completion time. (d) What is the probability of completing the project on or before 30 weeks'? (e) If the probability of completing the project is 0.85-090 find the expected project completion time.
Q4: Consider the following table summarizing the details of a project Activity Predecessor(s) Duration (weeks) Most likely time Pessimistic time 8. Optimistic time A 3 6. 9. 4. 4. 5. 6. 3 3. 9. 4. 11 8. C,D C,D.E F 9. 6. H 3. 9. (a) Construct the project network. (b) Find the expected duration and variance of each activity. (c) Find the critical path and the expected projeet completion time. (d) What is the probability of completing the project on or before 30 weeks'? (e) If the probability of completing the project is 0.85-090 find the expected project completion time.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
I need the answer as soon as possible
![Q4: Consider the following table summarizing the details of a project
Predecessor(s)
Duration (weeks)
Most likely time
5
Activity
Optimistic time
3
6.
Pessimistic time
8
9.
4.
D
4.
5.
6.
3
8.
B.
3.
9.
F
4
11
6.
C,D
8.
6.
C,D.E
2.
(a) Construct the project network.
(b) Find the expected duration and variance of each activity.
(c) Find the critical path and the expected projeet completion time.
(d) What is the probability of completing the proiect on or before 30 weeks'?
(e) If the probability of completing the project is 0.85.090 find the expected project completion time.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F2331ee75-7a13-4eed-9bfb-7970f53f6adf%2Fee252cd2-ca0a-429d-bf12-3ad815ec20ef%2Fba7gc3t_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Q4: Consider the following table summarizing the details of a project
Predecessor(s)
Duration (weeks)
Most likely time
5
Activity
Optimistic time
3
6.
Pessimistic time
8
9.
4.
D
4.
5.
6.
3
8.
B.
3.
9.
F
4
11
6.
C,D
8.
6.
C,D.E
2.
(a) Construct the project network.
(b) Find the expected duration and variance of each activity.
(c) Find the critical path and the expected projeet completion time.
(d) What is the probability of completing the proiect on or before 30 weeks'?
(e) If the probability of completing the project is 0.85.090 find the expected project completion time.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning