Given a project with the following characteristics, answer the following questions: 1. You are the project manager of a project to build fancy birdhouses. 2. You are to build two birdhouses a month for 12 months. 3. Each birdhouse is planned to cost $100. 4. Your project is scheduled to last for 12 months. 5. It is the beginning of month 10. 6. You have built 20 birdhouses and your CPI is 0.9091. a.Based on the given characteristics, justify the performances of the project in terms of cost and schedule B. Compute the schedule performance index (SPI) of the project. C.You are required to compute the project’s percentage of completion and present it to the Senior management. Derive the necessary formula for the percentage. Enable GingerCannot connect to Ginger Check your internet connection or reload the browserDisable in this text fieldRephraseRephrase current sentence3Edit in Ginger×
Given a project with the following characteristics, answer the following questions: 1. You are the project manager of a project to build fancy birdhouses. 2. You are to build two birdhouses a month for 12 months. 3. Each birdhouse is planned to cost $100. 4. Your project is scheduled to last for 12 months. 5. It is the beginning of month 10.
6. You have built 20 birdhouses and your CPI is 0.9091.
a.Based on the given characteristics, justify the performances of the project in terms of cost and
Enable GingerCannot connect to Ginger Check your internet connection
or reload the browserDisable in this text fieldRephraseRephrase current sentence3Edit in Ginger×
Trending now
This is a popular solution!
Step by step
Solved in 2 steps