Find the Volume of material to be removed from the total trench is ?

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Find the Volume of material to be removed from the total trench is ?
Side View
Existing
127.92
127.92
94.2² =
Cross Section
Station:
27
136.52
Elev. 'A'
3.61
13/0.21.
Drawing not to scale
Existing Ground
Pipe to be repaired
64.000m
Your given distance from end
ياء
Cross Section
Here is a cross-section view of your pipe at your assigned chainage.
The incline on the left side is at a slope of 1 to 1, or 45°.
The incline on the right side is determined by a distance from the center line of the job. Determine the grade of this
slope.
To determine the end area, use a baseline of 2.000 meters below the calculated bottom of pipe.
Elev. 'A' + 4.00m
130.10.2l
16
1.42~
C/L
Invert of Pipe
m
2.00m →
260m
6.00m
Elev. 'B'
*
85.000 m
135.10
1.00m-1.00m-
124.31
1.19
122.31
Name: Attique Chades. N. 27
21m
→>
16.00m
Elev. 'C'
Slope Grade 75.9%
Existing
end elevatien
= 123.12m
137.70
Existing Ground
126-31
124.31%,
15.000m
å
263.5²
Elev. 'C
BE11
Baseline
Transcribed Image Text:Side View Existing 127.92 127.92 94.2² = Cross Section Station: 27 136.52 Elev. 'A' 3.61 13/0.21. Drawing not to scale Existing Ground Pipe to be repaired 64.000m Your given distance from end ياء Cross Section Here is a cross-section view of your pipe at your assigned chainage. The incline on the left side is at a slope of 1 to 1, or 45°. The incline on the right side is determined by a distance from the center line of the job. Determine the grade of this slope. To determine the end area, use a baseline of 2.000 meters below the calculated bottom of pipe. Elev. 'A' + 4.00m 130.10.2l 16 1.42~ C/L Invert of Pipe m 2.00m → 260m 6.00m Elev. 'B' * 85.000 m 135.10 1.00m-1.00m- 124.31 1.19 122.31 Name: Attique Chades. N. 27 21m →> 16.00m Elev. 'C' Slope Grade 75.9% Existing end elevatien = 123.12m 137.70 Existing Ground 126-31 124.31%, 15.000m å 263.5² Elev. 'C BE11 Baseline
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning