Figure 11-2 Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Engineering £1,000,000 Setups 900,000 Machining 2,000,000 Inspection 800,000 Providing space 250,000 Providing utilities 180,000 Activity drivers for each activity have been identified and their practical capacities listed: Machine hours 25,000 Setups 200 Engineering hours 5,000 Inspection hours 2,500 The costs of facility-level activities are assigned using machine hours. Refer to Figure 11-2. What is the cost pool rate for the facility-level activities? A. £17.20 per machine hour B. £13,500.00 per setup C. £97.20 per machine hour D. £80.00 per machine hour
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:
Engineering £1,000,000
Setups 900,000
Machining 2,000,000
Inspection 800,000
Providing space 250,000
Providing utilities 180,000
Activity drivers for each activity have been identified and their practical capacities listed:
Machine hours 25,000
Setups 200
Engineering hours 5,000
Inspection hours 2,500
The costs of facility-level activities are assigned using machine hours.
Refer to Figure 11-2. What is the cost pool rate for the facility-level activities?
A. £17.20 per machine hour
B. £13,500.00 per setup
C. £97.20 per machine hour
D. £80.00 per machine hour
Trending now
This is a popular solution!
Step by step
Solved in 4 steps