Exercises Days 1. Use the following information to compress one time unit per move using the least- cost method. Reduce the schedule until you reach the crash point of the network... For each move identify what activity or activities were crashed and the adjusted total cost. Note: The correct normal project duration, critical path, and total direct cost are provided. 1211098 Act. A TMODRY B C F A B 3 Crash Cost (slope) 50 100 60 60 70 0 Indirect Cost ($) 500 425 350 275 200 B 3 с D 3 E 4 Maximum Crash Time 1 1 2 2 1 0 The question is missing the indirect cost, here are the indirect cost for the project F 8 1x Normal Time 3 3 Initial project duration: 12 4 3 4 Normal Cost 150 100 200 200 200 150 Total direct cost: $1,000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Exercises
Days
1. Use the following information to compress one time unit per move using the least-
cost method. Reduce the schedule until you reach the crash point of the network.
For each move identify what activity or activities were crashed and the adjusted
total cost.
O 12
11
10
9
8
Act.
A
В
BLOWF
Note: The correct normal project duration, critical path, and total direct cost are
provided.
A
B
3
Crash Cost (slope)
50
100
60
60
70
0
B
88
3
Indirect
Cost ($)
500
425
350
275
200
C
4
D
3
Maximum Crash Time
E
4
2
2
1
0
The question is missing the indirect cost,
here are the indirect cost for the project
F
1x
Normal Time
3
3
4
3
4
Initial
project duration: 12
1
Total direct cost: $1,000
Normal Cost
150
100
200
200
200
150
Focus
=
Transcribed Image Text:Exercises Days 1. Use the following information to compress one time unit per move using the least- cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total cost. O 12 11 10 9 8 Act. A В BLOWF Note: The correct normal project duration, critical path, and total direct cost are provided. A B 3 Crash Cost (slope) 50 100 60 60 70 0 B 88 3 Indirect Cost ($) 500 425 350 275 200 C 4 D 3 Maximum Crash Time E 4 2 2 1 0 The question is missing the indirect cost, here are the indirect cost for the project F 1x Normal Time 3 3 4 3 4 Initial project duration: 12 1 Total direct cost: $1,000 Normal Cost 150 100 200 200 200 150 Focus =
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.