A. Construct a network for the project outlined below and determine the critical path time. B. Critical path: C. Complete the table below: Activity ao o - - - A B C D E F ES LS EF LF Slack Critical Path

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Problem 2:
Activity
A
B
C
D
E
F
Activity
A
B
C
D
E
F
D.
E.
F.
G.
Immediate
Predecessor
B
B
A,B
C,D,E
ES
A. Construct a network for the project outlined below and determine the critical path time.
B. Critical path:
C. Complete the table below:
LS
Time
Time of completion:
Shortest Completion Possible Time:
Cost of the Normal Duration:
Crash Cost:
6
3
8
10
12
4
Normal cost
EF
P110
P130
P210
P160
P180
P170
Crash Duration
LF
4
1
4
5
10
3
Slack
Crash Cost
P180
P150
P260
P180
P230
P200
Critical Path
Transcribed Image Text:Problem 2: Activity A B C D E F Activity A B C D E F D. E. F. G. Immediate Predecessor B B A,B C,D,E ES A. Construct a network for the project outlined below and determine the critical path time. B. Critical path: C. Complete the table below: LS Time Time of completion: Shortest Completion Possible Time: Cost of the Normal Duration: Crash Cost: 6 3 8 10 12 4 Normal cost EF P110 P130 P210 P160 P180 P170 Crash Duration LF 4 1 4 5 10 3 Slack Crash Cost P180 P150 P260 P180 P230 P200 Critical Path
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.