Duration Activity IPA Optimistic Realistic Pessimistic 2 8 19 12 C A 10 12 19 B 18 23 C 7 16 19 F B,D 12 29 C,D 10 15 23

MARKETING 2018
19th Edition
ISBN:9780357033753
Author:Pride
Publisher:Pride
Chapter11: Product Concepts, Branding, And Packaging
Section11.1: Gaga: Not Just A Lady
Problem 1VC
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
Draw AON network for the given data. Compare all the available paths. Calculate expected duration and standard deviation for each path. Considering all available paths, what is the duration of project with at least 85% confidence level.
Duration
Activity
IPA
Optimistic
Realistic
Pessimistic
A
8
19
A
12
A
10
12
19
18
23
C
7
16
19
F
B,D
5
12
29
G
C,D
10
15
23
6.
Transcribed Image Text:Duration Activity IPA Optimistic Realistic Pessimistic A 8 19 A 12 A 10 12 19 18 23 C 7 16 19 F B,D 5 12 29 G C,D 10 15 23 6.
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College