Draw a network diagram for this process. What is the total expected time in hours for this recipe to be completed? hours Show the activity schedule. There is only one non-critical activity, which is Activity and has a slack time of hours If Dr. Kay can obtain the batter already fermented and ready to cook, how much active cooking time should she put aside for making the White Dhokla? hour(s).
Draw a network diagram for this process. What is the total expected time in hours for this recipe to be completed? hours Show the activity schedule. There is only one non-critical activity, which is Activity and has a slack time of hours If Dr. Kay can obtain the batter already fermented and ready to cook, how much active cooking time should she put aside for making the White Dhokla? hour(s).
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Chapter 3. Dr. Kay is learning how to make some traditional Indian food and comes upon this recipe for a childhood favorite (White Dhokla): https://recipes.timesofindia.com/us/recipes/white-dhokla/rs59190882.cms (Links to an external site.). In an effort to remain organized she sorts out the steps of the recipe to get an estimate of how much time it would take her to complete the recipe.
|
|
|
Immediate |
Time |
Activity |
Description |
|
Predecessor |
(Hours) |
A |
Soak lentils & rice |
-- |
8 |
|
B |
Grind lentil-rice mixture |
A |
0.5 |
|
C |
Ferment lentil-rice mixture |
B |
8 |
|
D |
Heat the steamer |
C |
0.25 |
|
E |
Prepare the pans with mixture |
C |
0.25 |
|
F |
Steam the pans |
D, E |
1 |
|
G |
Prepare tempering |
E |
0.25 |
|
H |
Temper, Cool, and serve |
F, G |
0.25 |
- Draw a network diagram for this process. What is the total expected time in hours for this recipe to be completed? hours
- Show the activity
schedule. There is only one non-critical activity, which is Activity and has a slack time of hours - If Dr. Kay can obtain the batter already fermented and ready to cook, how much active cooking time should she put aside for making the White Dhokla? hour(s).
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 6 steps with 4 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.