a) The probability of completing the critical path in
12 weeks (or less), as the client desires. (b) The probability of completing the critical path in
13 weeks (or less). c) The probability of completing the critical path in
16 weeks (or less), the client’s drop-dead date.
a) The probability of completing the critical path in 12 weeks (or less), as the client desires. (b) The probability of completing the critical path in 13 weeks (or less). c) The probability of completing the critical path in 16 weeks (or less), the client’s drop-dead date.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
1.16
Given an auditing project with the following activities,
please refer to the first pic
find:
(a) The probability of completing the critical path in
12 weeks (or less), as the client desires.
(b) The probability of completing the critical path in 13 weeks (or less).
c) The probability of completing the critical path in 16 weeks (or less), the
client’s drop-dead date.
(d) The number of weeks required to assure a 92.5 percent chance of completing the critical path, as guaranteed by the auditing firm.

Transcribed Image Text:Activity
a, add
b, balance
c, count
d, deduct
e, edit
f, finance
g, group
h, hold
Standard
Deviation
2
1
0
3
1
2
2
0
Critical?
yes
yes
yes
yes
yes
Duration
2
3
4
2
1
6
4
2
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step 1 Introduction;-
VIEWStep 2 Finding the values to find the probability:-
VIEWStep 3 Calculating Probability of completing the critical path in
12 weeks (or less):-
VIEWStep 4 Calculating probability of completing the critical path in
13 weeks (or less).
VIEWStep 5 Calculating probability of completing the critical path in
16 weeks (or less)
VIEWStep 6 ANSWERS
VIEWStep by step
Solved in 6 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.