Direction: Determine the statement of the problem, solution to the problem and conlusion of the given case. Case No.1:
Direction: Determine the statement of the problem, solution to the problem and conlusion of the given case.
Case No.1:
Robert L. Frank Construction Company
It was Friday afternoon, a late November day in 2003, and Ron Katz, a purchasing agent for Robert L. Frank Construction, poured over the latest earned value measurement reports. The results kept pointing out the same fact; the Lewis project was seriously over budget. Man-hours expended to date were running 30 percent over the projection and, despite this fact, the project was not progressing sufficiently to satisfy the customer. Material deliveries had experienced several slippages, and the unofficial indication from the project
Each day for the past few months as he reviewed the daily printout of project time charges, he would note that the purchasing and expediting departments were working on the Lewis project, even though it was not an unusually large project, dollarwise, for Frank. Two years earlier, Frank was working on a $300 million contract, a $100 million contract and a $50 million contract concurrently with the Frank Chicago purchasing department responsible
for all the purchasing, inspection, and expediting on all three contracts. The Lewis project was the largest project in house and was valued at only $90 million. What made this project so different from previous contracts and caused such problems? There was little Katz felt
that he could do to correct the situation. All that could be done was to understand what had occurred in an effort to prevent a recurrence. He began to write his man-hour report for requested by the project manager the next day.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps