d. Use the calculated cycle time. Assign tasks to workstations on the basis of most following tasks. Use shortest processing time as a tiebreaker. If ties still exist, assume indifference in choice. Work stations Following Tasks II II IV e. Compute the percent idle time and percent efficiency for the assignment in part d. Note: if the calculated cycle time and the actual bottleneck station time are different, use the actual bottleneck time in your calculations. (Round your answers to 2 decimal places) Idle percentage Efficiency %
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 230 units per 8-hour day. Task times and precedence relationships are as follows:
Task | Duration (minutes) |
Immediate Predecessor |
a | 0.2 | - |
b | 0.6 | a |
c | 0.4 | b |
d | 0.7 | - |
e | 1.6 | d |
f | 1.8 | c |
g | 2 | e, f |
Since you have posted a question with multiple sub-parts, we will solve the first three subparts for you. To get the remaining sub-part solved please repost the complete question and mention the sub-parts to be solved.
Assigning each task to a workstation within an assembly line to fulfill the necessary production rate and to achieve a minimum amount of idle time is known as assembly line balance. Line balancing is the process by which tasks are delegated to work stations along the assembly line such that each has roughly the same amount of work.
The advantages of assembly line balancing are:
- improved effectiveness
- A rise in productivity
- Potentially higher earnings and lower costs
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 1 images