(d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) =                (e) Develop an activity schedule for the crashed project. Activity Earliest Start Latest Start Earliest Finish Latest Finish Slack A           B           C           D           E           F

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Question
I ONLY NEED HELP WITH PART. D,E,F. Please and thank you
 
Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities.
      Time (weeks) Cost ($1,000s)
Activity Description Immediate
Predecessor
Normal Crash Normal Crash
A Plan needs   10 8 30 70
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60  
(a)
Develop a project network.
A project network with 8 activities and 8 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B and to activity C.
  • Activity B is connected to activity D.
  • Activity C is connected to activity E.
  • Activity D is connected to activity F.
  • Activity E is connected to activity F.
  • Activity F is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
 
A project network with 8 activities and 8 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B and to activity D.
  • Activity B is connected to activity C.
  • Activity C is connected to activity F.
  • Activity D is connected to activity E.
  • Activity E is connected to activity F.
  • Activity F is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
 
A project network with 8 activities and 8 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B and to activity D.
  • Activity B is connected to activity E.
  • Activity C is connected to activity F.
  • Activity D is connected to activity C.
  • Activity E is connected to activity F.
  • Activity F is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
 
A project network with 8 activities and 8 directed arcs is shown.
  • Activity Start is connected to activity A.
  • Activity A is connected to activity B and to activity C.
  • Activity B is connected to activity E.
  • Activity C is connected to activity D.
  • Activity D is connected to activity F.
  • Activity E is connected to activity F.
  • Activity F is connected to activity Finish.
  • Activity Finish has no arcs directed to other activities.
(b)
Develop an activity schedule.
Activity Earliest
Start
Latest
Start
Earliest
Finish
Latest
Finish
Slack
A          
B          
C          
D          
E          
F          
(c)
What are the critical activities? (Enter your answers as a comma-separated list.)
A,B,C,F
 
 
 
What is the expected project completion time (in weeks)?
  weeks
(d)
Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost?
(A, B, C, D, E) = 
 
 
 
 
 
 
 
 
(e)
Develop an activity schedule for the crashed project.
Activity Earliest
Start
Latest
Start
Earliest
Finish
Latest
Finish
Slack
A          
B          
C          
D          
E          
F          
(f)
What added project cost (in thousands of dollars) is required to meet the si
x-month completion time?                   thousands of dollars
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 17 images

Blurred answer
Knowledge Booster
Introduction to Business messages
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.