Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings t Axelrod under the contract were as follows:

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 9MC
icon
Related questions
Question
Req 1 and 2
Req 3
Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in
the balance sheet at the end of 2021 and 2022 as either cost in excess of billings or billings in excess of costs.
Balance Sheet (Partial)
Current assets:
Costs less loss in excess of billings
Current liabilities:
Billings in excess of costs and profit
2021
< Req 1 and 2
2022
Req 3 >
Transcribed Image Text:Req 1 and 2 Req 3 Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2021 and 2022 as either cost in excess of billings or billings in excess of costs. Balance Sheet (Partial) Current assets: Costs less loss in excess of billings Current liabilities: Billings in excess of costs and profit 2021 < Req 1 and 2 2022 Req 3 >
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story
office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total
contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated
percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to
Axelrod under the contract were as follows:
Percentage of completion
Costs incurred to date
Estimated costs to complete
Billings to Axelrod, to date
Req 1 and 2
Complete this question by entering your answers in the tabs below.
Req 3
At 12-31-2021 At 12-31-2022
10%
$ 350,000
3,150,000
720,000
$2,500,000
1,700,000
2,170,000
Year
2021
2022
2023
Total project profit (loss)
Required:
1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the
contract does not qualify for revenue recognition over time.
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be
recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the
balance sheet at the end of 2021 and 2022 as either cost in excess of billings or billings in excess of costs.
$
60%
< Req 1 and 2
At 12-31-2023
1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that
the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according
to percentage of completion, compute gross profit or loss to be recognized in each of the three years. (Leave no cells blank -
be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.)
0 $
Req 1
Req 2
Gross Profit (Loss) Recognized Gross Profit (Loss) Recognized
("Upon Completion")
("Over Time")
$
0 $
100%
$4,250,000
4,000,000
Req 3 >
0
50,000
50,000
Show less
Transcribed Image Text:Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Req 1 and 2 Complete this question by entering your answers in the tabs below. Req 3 At 12-31-2021 At 12-31-2022 10% $ 350,000 3,150,000 720,000 $2,500,000 1,700,000 2,170,000 Year 2021 2022 2023 Total project profit (loss) Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2021 and 2022 as either cost in excess of billings or billings in excess of costs. $ 60% < Req 1 and 2 At 12-31-2023 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. (Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.) 0 $ Req 1 Req 2 Gross Profit (Loss) Recognized Gross Profit (Loss) Recognized ("Upon Completion") ("Over Time") $ 0 $ 100% $4,250,000 4,000,000 Req 3 > 0 50,000 50,000 Show less
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L