YellowStone Construction is constructing an office building under contract for LimeStone Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1300000 each quarter. The total contract price is $15600000 and YellowStone estimates total costs of $17500000. YellowStone estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, YellowStone Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $17750000 due to unanticipated price increases. YellowStone Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the total costs of construction are $18500000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that YellowStone will recognize for the year ended December 31, 2023? Revenue Expenses A. $3900000 $ 5187500 B. $4625000 $ 4625000 C. $3900000 $ 4625000 D. $15600000 $18500000
YellowStone Construction is constructing an office building under contract for LimeStone Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1300000 each quarter. The total contract price is $15600000 and YellowStone estimates total costs of $17500000. YellowStone estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, YellowStone Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $17750000 due to unanticipated price increases.
YellowStone Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the total costs of construction are $18500000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that YellowStone will recognize for the year ended December 31, 2023?
Revenue | Expenses |
A. | $3900000 | $ 5187500 |
B. | $4625000 | $ 4625000 |
C. | $3900000 | $ 4625000 |
D. | $15600000 |
$18500000 |
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)