On July 1, 2025, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2027, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2025, 2026, and 2027. NOTE: The company's fiscal year aligns with the calendar year. The phrase "to date" that is used in the contract details below, as well as in the answer table, means up to the present time. Pay attention to the years that you're working with! Total contract price $ 2,400,000 Contract costs incurred to date $ Estimated costs to complete the contract Progress Billings to Gumbel during year At 12/31/25 300,000 1,200,000 300,000 1,100,000 At 12/31/26 At 12/31/27 $1,220,000 $2,150,000 800,000 800,000 Instructions a. b. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2025, 2026, and 2027. (Ignore income taxes.) Using the cost recovery method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2025, 2026, and 2027. (Ignore income taxes.)

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
On July 1, 2025, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. On July 1,
Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2027, the
building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to
complete the contract, and accumulated billings to Gumbel for 2025, 2026, and 2027.
NOTE: The company's fiscal year aligns with the calendar year. The phrase "to date" that is used in the contract
details below, as well as in the answer table, means up to the present time. Pay attention to the years that you're
working with!
Total contract price
$
2,400,000
Contract costs incurred to date
$
Estimated costs to complete the contract
Progress Billings to Gumbel during year
At 12/31/25
300,000
1,200,000
300,000
1,100,000
At 12/31/26 At 12/31/27
$1,220,000 $2,150,000
800,000
800,000
Instructions
a.
b.
Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be
recognized as a result of this contract for the years ended December 31, 2025, 2026, and 2027. (Ignore
income taxes.)
Using the cost recovery method, prepare schedules to compute the profit or loss to be recognized as a
result of this contract for the years ended December 31, 2025, 2026, and 2027. (Ignore income taxes.)
Transcribed Image Text:On July 1, 2025, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2027, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2025, 2026, and 2027. NOTE: The company's fiscal year aligns with the calendar year. The phrase "to date" that is used in the contract details below, as well as in the answer table, means up to the present time. Pay attention to the years that you're working with! Total contract price $ 2,400,000 Contract costs incurred to date $ Estimated costs to complete the contract Progress Billings to Gumbel during year At 12/31/25 300,000 1,200,000 300,000 1,100,000 At 12/31/26 At 12/31/27 $1,220,000 $2,150,000 800,000 800,000 Instructions a. b. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2025, 2026, and 2027. (Ignore income taxes.) Using the cost recovery method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2025, 2026, and 2027. (Ignore income taxes.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education