A&B Construction enters into a contract to construct a bridge for $1,400,000. At the outset, A&B estimates that it will cost $1,200,000 to build the bridge. Actual costs in 2017 are $540,000. Actual costs in 2018 are less than expected an amount to $600,000. The profits reported under the completed contract and percent of completion methods for each year would be: Select one: Completed Contract Percentage of Completion O a. 2017 2018 2017 2018 $0 $200,000 $90,000 $170,000 O b. Completed Contract Percentage of Completion 2017 2018 2017 2018 ՏՈ $260.000 $90.000 $170.000

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
A&B Construction enters into a contract to construct a bridge for $1,400,000. At the outset, A&B estimates that it will
cost $1,200,000 to build the bridge. Actual costs in 2017 are $540,000. Actual costs in 2018 are less than expected and
amount to $600,000. The profits reported under the completed contract and percent of completion methods for each
year would be:
Select one:
Completed Contract
Percentage of Completion
○ a.
2017
2018
2017
2018
$0
$200,000
$90,000
$170,000
O b.
Completed Contract
Percentage of Completion
2017
2018
2017
2018
$0
$260,000
$90,000
$170,000
Completed Contract
Percentage of Completion
2017
2018
2017
$0
$260,000
$123,000
2018
$197,000
○ d.
Completed Contract
Percentage of Completion
2017
2018
2017
$0
$260,000
$90,000
2018
$110,000
Transcribed Image Text:A&B Construction enters into a contract to construct a bridge for $1,400,000. At the outset, A&B estimates that it will cost $1,200,000 to build the bridge. Actual costs in 2017 are $540,000. Actual costs in 2018 are less than expected and amount to $600,000. The profits reported under the completed contract and percent of completion methods for each year would be: Select one: Completed Contract Percentage of Completion ○ a. 2017 2018 2017 2018 $0 $200,000 $90,000 $170,000 O b. Completed Contract Percentage of Completion 2017 2018 2017 2018 $0 $260,000 $90,000 $170,000 Completed Contract Percentage of Completion 2017 2018 2017 $0 $260,000 $123,000 2018 $197,000 ○ d. Completed Contract Percentage of Completion 2017 2018 2017 $0 $260,000 $90,000 2018 $110,000
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education