In 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $910,000. Sunland uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2025, are shown below. Balance Sheet Accounts receivable Construction in process Less: Billings Costs and recognized profit in excess of billings a) Income Statement $71,000 65,600 Portion of contract billings collected $ Income (before tax) on the contract recognized in 2025 $24,850 How much cash was collected in 2025 on this contract? $18,000 5,400

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Domestic 

In 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $910,000. Sunland
uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the
proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this
contract at December 31, 2025, are shown below.
Accounts receivable
Construction in process
Less: Billings
Costs and recognized profit in excess of billings
Balance Sheet
(a)
Income Statement
Income (before tax) on the contract recognized in 2025
$71,000
Portion of contract billings collected
eTextbook and Media
65,600
How much cash was collected in 2025 on this contract?
$18,000
5,400
$24,850
Transcribed Image Text:In 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $910,000. Sunland uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2025, are shown below. Accounts receivable Construction in process Less: Billings Costs and recognized profit in excess of billings Balance Sheet (a) Income Statement Income (before tax) on the contract recognized in 2025 $71,000 Portion of contract billings collected eTextbook and Media 65,600 How much cash was collected in 2025 on this contract? $18,000 5,400 $24,850
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Revenue Recognition
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education