On January 1, 2018, Liquid Company accepted a long-term construction project for an ini contract price ofP2,000,000 to be completed on June 30, 2020. On January 1, 2019, the contr. price was increased toP3,000,000 by reason of change in the design of the project. The outcor of the construction contract can be estimated reliably. The project was completed on Decemb 31, 2020 which resulted to penalty amounting toP400,000. The entity provided the following da concerning the direct costs related to the said project for 2018and 2019: 2018 2019 Costs during the year 880,000 1,360,000 Remaining estimated costs to complete at year-end 1,320,000 560,000

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
On January 1, 2018, Liquid Company accepted a long-term construction project for an initial
contract price ofP2,000,000 to be completed on June 30, 2020. On January 1, 2019, the contract
price was increased toP3,000,000 by reason of change in the design of the project. The outcome
of the construction contract can be estimated reliably. The project was completed on December
31, 2020 which resulted to penalty amounting toP400,000. The entity provided the following data
concerning the direct costs related to the said project for 2018and 2019:
2018
2019
Costs during the year
880,000
1,360,000
Remaining estimated costs to complete at year-end
1,320,000
560,000
What is the construction revenue for the year ended December 31, 2018?
Transcribed Image Text:On January 1, 2018, Liquid Company accepted a long-term construction project for an initial contract price ofP2,000,000 to be completed on June 30, 2020. On January 1, 2019, the contract price was increased toP3,000,000 by reason of change in the design of the project. The outcome of the construction contract can be estimated reliably. The project was completed on December 31, 2020 which resulted to penalty amounting toP400,000. The entity provided the following data concerning the direct costs related to the said project for 2018and 2019: 2018 2019 Costs during the year 880,000 1,360,000 Remaining estimated costs to complete at year-end 1,320,000 560,000 What is the construction revenue for the year ended December 31, 2018?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education