Complete the table below. Number of hours for plant A Number of hours for plant B Orders 2 3
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: Material requirements planning - is based on the production planning, scheduling, and inventory…
Q: Below is information related to: historical average processing times for Products A and B historical…
A:
Q: I. II. III. A B C D E F Work Element Tan leather Dye leather Shape Case Mold hinges & fixtures…
A: Given data:
Q: Explain what is meant by the theory of constraints in process strategy ?
A: To be determined: what is meant by the theory of constraints in process strategy
Q: Problem 1 The F/C production line manufactures the Flask/cap product. Demand for this product is…
A: Given data, Demand for the product 57k - 5 th week 35k - 6 th week 80 k - 7 th week Flask/cap -…
Q: Explain in terms of scheduling how does synchronous manufacturing vary from MRP
A: Coordinated Mfg (CM) is a lesser-known manufacturing strategy that evaluates and monitors an…
Q: Problem 13-2 (Algo) The following table lists the components needed to assemble an end item, lead…
A: Given-
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A:
Q: a. If 43 units of the end item are to be assembled, how many additional units of B are needed?…
A: As per the question, I wouldn't develop any MRP plan, here, a total of 43 units of the end item is…
Q: Problem 2 Below is information related to: historical average processing times for Products A and B…
A:
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: Given data
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: a. Net Requirement of End Item = 18-0 = 18 Net Requirement of B = 18*2 - 10 = 36-10 = 26 Net…
Q: he following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: Answer: Below is the given data in a tabular and diagrammatical form (Note: We simply have shown…
Q: How does ERP link the departments together?
A: Enterprise Resource Planning (ERP) is a software system that integrates various departments and…
Q: Create a data sheet for ES, EF, LS, LF, TF, FF, INTF and Independent Float. Find the critical path…
A: WE ARE ALLOWED TO DO FIRST THREE SUB PARTS ONLY: THE ANSWER IS AS BELOW:
Q: The Service Transaction Is Conducted Remotely Developments in telecommunications, online technology,…
A: Many businesses are moving to the digital platform because of increased penetration of smartphones…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: An MRP plan helps to keep the inventory levels optimal. Optimal inventory level helps to reduce the…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: Based on the given table, we prepare a product tree structure as shown below: Answer: 392
Q: Q2: Six processes are to be laid out in six areas along a long corridor at Linda Babat Accounting…
A: Every pair of connected nodes in the network is associated with a specific demand. The demand will…
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: (a): Units of end item required = 17. Thus 17*2 = 34 units of B, 17 units of C and 17*3 = 51 units…
Q: Alvis Construction Supply Company has a department that manufactures wood trusses (wood frames used…
A: The following data of the generation of trusses in Feb: Work-in-process inventory, February 1…
Q: A steel workshop wants to improve its productivity by making small metal hooks by changing the…
A: Given that: Activities Duration (in seconds) Predecessor A 17 None B 15 A C 18 B D 8 B…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: FORMULA TO BE USED Gross requirement = Required Item Quantity * Usage Rate Net requirement…
Q: Part 1: Use PowerPoint to create a WBS in chart form for a web development project of your choosing…
A: Work Breakdown StructureThe project deliverables, activities, and tasks are broken down into a Work…
Q: a. Construct a precedence diagram and compute the lead time for the process. b. If the demand for…
A:
Q: Explain the following functions of MRP 1.forecasting 2.reducing waste 3.floor-control and…
A: Material requirement planning is a process of planning, scheduling and managing the inventory in…
Q: nd: None ot ze WC Setup (min) 50 30 45 Bill of Mate Run Time (min/unit 4.0
A: Given: Data for routing file: Part Lot size WC Setup(min) Run Time Z 50 30 45 4.0 D 80 40 30…
![A supplier for the automobile industry manufactures car and truck frames at two different plants. How many hours should each plant be scheduled to operate to exactly fill each of the
orders in the right table? The production rates (in frames per hour) for each plant are given in the left table.
Plant
A
B
Car Frames
5
10
Complete the table below.
Number of hours for plant A
Number of hours for plant B
Truck Frames
5
4
1
Car frames
Truck frames
Orders
2
1
910
436
3
Orders
2
920
434
3
1480
1138](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fe2f78f6f-d101-4a55-a6f8-e9c9aeff3d81%2Fcba9bd31-afff-49d7-ad5f-f1b1af805481%2Fhhd4g9q_processed.png&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Here, I would determine the number of hours for plant A and the number of hours for plant B,
Let me consider, for order 1, The number of hours for plant A is X1, the number of hours for Plant B is Y1,
For order 2, the number of hours for Plant A is X2, the number of hours for Plant B is Y2,
For order 3, the number of hours for Plant A is X3, the number of hours for Plant B is Y3,
Here, I would set up the linear system, then solve this problem,
For order 1,
For order 2,
For order 3,
Now, I would solve this system below,
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
- XYZ Leather Company manufactures and sells two products, wallets and belts, in its two-department plant. Operating data pertaining to the two products are as follows: Wallets Belts Selling price per unit P30 P50 Cost per unit: Variable manufacturing costs P8 P15 Variable marketing costs P2 P3 Fixed manufacturing costs P5 P5 Fixed marketing costs P6 P1 Cutting Finishing…The Chineke Group of Company manufactures two products, namely product B and product P, and provides you with the following information: Prod. B Prod. P Selling price per unit 80.00 50.00 Less cost of sales: Direct material A @ R5.00 per kg 15.00 10.00 Direct material B @ R4.00 per kg 8.00 12.00 Direct labour @ R6.00 per hour 12.00 6.00 Variable manufacturing overhead @ R5.00 per labour hour 10.00 5.00 Fixed manufacturing overhead per unit 5.00 5.00 Gross profit 30.00 12.00 Less sales & administrative costs: Variable 6.00 4.00 Fixed 10.00 5.00 Net profit per unit 14.00 3.00 Take note of the following constraints: Material A available 360 kg Material B available 360 kg Labour hours available…what is the correct answer?
- Tuff-Rider, Inc., manufactures touring bikes and mountainbikes in a variety of frame sizes, colors, and component com-binations. Identical bicycles are produced in lots of 100. Theprojected demand, lot size, and time standards are shown inthe following table: Item Touring MountainDemand forecast 5,000 units/year 10,000 units/yearLot size 100 units 100 unitsStandard processing time .25 hour/unit .50 hour/unitStandard setup time 2 hours/lot 3 hours/lot The shop currently works 8 hours a day, 5 days a week,50 weeks a year. It operates five workstations, each producingone bicycle in the time shown in the table. The shop main-tains a 15 percent capacity cushion. How many workstationswill be required next year to meet expected demand withoutusing overtime and without decreasing the firm’s currentcapacity cushion?What is OEE and also calculate the OEE from the given data in below table Items Data Shift Length 8 Hours Breaks (2) 15 minute and (1) 30 minute Downtime 47 minutes ideal Cycle Time 1.0 seconds Total Count 19,271 widgets Reject Count 423 widgetsXYZ Corporation operates two plants, each of which has a capacity of 170 units per day. Each day, XYZ must ship their product to each of four customers. Customers A, B, and C each have a demand of 12 units per day while customer D has a demand of 304 units per day. The cost of shipping one unit of each product from each of the two plants to each of the customers is shown in the table below. Customer A Customer B Customer C Customer D Plant 1 20 15 14 24 Plant 2 25 25 23 19 a. How many units should XYZ ship from each plant to each customer? (Leave no cells blank-be certain to enter "O" wherever required. Round your answer to the nearest whole number.) Customer A Customer B Customer C Customer D Plant 1 Plant 2
- Motorking Corporation, a market leader in the production of specialized engine additives, is considering introducing a new "gas extender" product. This product is added to an automobile’s gasoline to extend mileage and reduce exhasut emissions. Motorking's manufacturing facility can produce 50,000 cases of the new product per year with a set-up cost of $100,000. The average variable cost per case would be $5. Large orders, (i.e., above 50,000 cases) will be subcontracted to a local refining company. Motorking has signed a secrecy agreement with the vendor that guards the basic process. The variable cost per case, if the new product is produced outside, is $9. Whether the product is manufactured by Motorking or by the vendor, there is a $12 per case cost for marketing and overhead. Motorking's production manager is considering three production levels for the new product: 50,000 cases, 75,000 cases, and 100,000 cases. The level of sales will depend on the state of the economy. Sales…Consider the following costs of Zula Ltd over the relevant range of 5 000 to 2 0000 units produced.Units produced 5 000 10 000 15 000 20 000Variable cost $200 000 ? ? ?Fixed cost $1 800 000 ? ? ?Total ? ? ? ?Cost per unitVariable cost ? ? ? ?Fixed cost ? ? ? ?Total ? ? ? ?RequiredComplete the above tableSawing 20 min/unit Sanding 20 min/unit Drilling 32 min/unit Welding 30 min/unit Assembly 93 min/unit Assembly 93 min/unit Assembly 93 min/unit A production process is shown in the figure above. The drilling operation occurs separately from, and simultaneously with the sawing and sanding operations. Welding starts when both drilling and sanding operations have been completed. After welding, a product needs to go through only one of the three assembly operations (the operations are in parallel, where parallel lines perform the exact same operation). Considering the process times at stations, what is the process time of the system (in min/unit)?
- The MacJunkin Company manufactures transmission parts. The current process uses 20 workers and produces 400 units per hour. You are considering changing the process with new manufacturing methods that increase output to 470 units per hour but will require 22 workers. Workers are paid at a rate of $15 per hour, and overhead is charged at 140% (or 1.4 times) labor costs. Finished switches sell for $80/unit. The details are as follows: Current Process New Process Output (Units/Hour) 400 470 Number of Workers 20 22 Material (Cost/Hour) $120 $150 A. What is the multifactor productivity ratio for the current process? B. What is the multifactor productivity ratio for the new process?The MacJunkin Company manufactures transmission parts. The current process uses 20 workers and produces 400 units per hour. You are considering changing the process with new manufacturing methods that increase output to 470 units per hour but will require 22 workers. Workers are paid at a rate of $15 per hour, and overhead is charged at 140% (or 1.4 times) labor costs. Finished switches sell for $80/unit. The details are as follows: Current Process New Process Output (Units/Hour) 400 470 Number of Workers 20 22 Material (Cost/Hour) $120 $150 These are the correct answers can you show me how to get these answers? A. What is the multifactor productivity ratio for the current process? 38.10 B. What is the multifactor productivity ratio for the new process? 39.92 Your answer is correct.The controller of Sandhill Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Total Total Month Maintenance Costs Machine Hours January $2,570 3,400 February 2,940 3,920 March 3,510 5,880 April 4,410 7,760 May 3,100 4,900 June 4,506 7,800
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)