Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job 1 2 3 4 5 Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is: Sequence 1 2 3 4 CR 5 Job The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 250. Job 1 2 3 4 5 Date Job Due Received Date 215 220 225 240 250 260 290 300 320 340 Duration (days) 30 20 40 50 20
Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job 1 2 3 4 5 Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is: Sequence 1 2 3 4 CR 5 Job The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 250. Job 1 2 3 4 5 Date Job Due Received Date 215 220 225 240 250 260 290 300 320 340 Duration (days) 30 20 40 50 20
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.)
Job
|
CR
|
1
|
enter your response here
|
Part 2
2
|
enter your response here
|
Part 3
3
|
enter your response here
|
Part 4
4
|
enter your response here
|
Part 5
5
|
enter your response here
|
Part 6
Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is:
Sequence
|
Job
|
1
|
▼
4
5
3
1
2
|
Part 7
2
|
▼
2
1
5
3
4
|
Part 8
3
|
▼
5
4
2
3
1
|
Part 9
4
|
▼
1
3
2
5
4
|
Part 10
5
|
▼
5
4
1
3
2
|
...
Question content area right
Part 1
The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day
250.
Job
|
Date Job Received
|
Due Date
|
Duration (days)
|
|
1
|
215
|
260
|
30
|
|
2
|
220
|
290
|
20
|
|
3
|
225
|
300
|
40
|
|
4
|
240
|
320
|
50
|
|
5
|
250
|
340
|
20
|
![# Critical Ratio (CR) Calculation and Job Sequencing
## Objective
Calculate the Critical Ratios (CR) for the given jobs and determine the sequence using the Critical Ratio scheduling rule. Note that all responses should be rounded to two decimal places.
## Job Information at Jeremy LaMontagne's Machine Center
The following jobs are waiting to be processed:
| Job | Date Job Received | Due Date | Duration (days) |
|-----|-------------------|----------|-----------------|
| 1 | 215 | 260 | 30 |
| 2 | 220 | 290 | 20 |
| 3 | 225 | 300 | 40 |
| 4 | 240 | 320 | 50 |
| 5 | 250 | 340 | 20 |
Today is day 250.
## Critical Ratio Calculation
1. **Formula for Critical Ratio (CR):**
\[ \text{CR} = \frac{\text{Time Remaining}}{\text{Work Remaining}} \]
Where:
\[ \text{Time Remaining} = \text{Due Date} - \text{Current Day} \]
\[ \text{Work Remaining} = \text{Duration (days)} \]
2. **Calculate the CR for each job:**
| Job | Time Remaining | Work Remaining | CR Calculation | CR |
|-----|----------------|----------------|----------------------------|------|
| 1 | 260 - 250 = 10 | 30 | CR = 10 / 30 | 0.33 |
| 2 | 290 - 250 = 40 | 20 | CR = 40 / 20 | 2.00 |
| 3 | 300 - 250 = 50 | 40 | CR = 50 / 40 | 1.25 |
| 4 | 320 - 250 = 70 | 50 | CR = 70 / 50 | 1.40 |
| 5 | 340 - 250 = 90 | 20 | CR = 90 / 20 | 4.50 |
3. **CRs Summarized:**
| Job | CR |
|-----|------|
| 1 | 0.33 |
|](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F135ae681-a644-4164-9b10-2ae2e87534da%2F18dd734b-d826-42b3-85a2-a01c4941f3f9%2Faxbkebs_processed.png&w=3840&q=75)
Transcribed Image Text:# Critical Ratio (CR) Calculation and Job Sequencing
## Objective
Calculate the Critical Ratios (CR) for the given jobs and determine the sequence using the Critical Ratio scheduling rule. Note that all responses should be rounded to two decimal places.
## Job Information at Jeremy LaMontagne's Machine Center
The following jobs are waiting to be processed:
| Job | Date Job Received | Due Date | Duration (days) |
|-----|-------------------|----------|-----------------|
| 1 | 215 | 260 | 30 |
| 2 | 220 | 290 | 20 |
| 3 | 225 | 300 | 40 |
| 4 | 240 | 320 | 50 |
| 5 | 250 | 340 | 20 |
Today is day 250.
## Critical Ratio Calculation
1. **Formula for Critical Ratio (CR):**
\[ \text{CR} = \frac{\text{Time Remaining}}{\text{Work Remaining}} \]
Where:
\[ \text{Time Remaining} = \text{Due Date} - \text{Current Day} \]
\[ \text{Work Remaining} = \text{Duration (days)} \]
2. **Calculate the CR for each job:**
| Job | Time Remaining | Work Remaining | CR Calculation | CR |
|-----|----------------|----------------|----------------------------|------|
| 1 | 260 - 250 = 10 | 30 | CR = 10 / 30 | 0.33 |
| 2 | 290 - 250 = 40 | 20 | CR = 40 / 20 | 2.00 |
| 3 | 300 - 250 = 50 | 40 | CR = 50 / 40 | 1.25 |
| 4 | 320 - 250 = 70 | 50 | CR = 70 / 50 | 1.40 |
| 5 | 340 - 250 = 90 | 20 | CR = 90 / 20 | 4.50 |
3. **CRs Summarized:**
| Job | CR |
|-----|------|
| 1 | 0.33 |
|
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.