Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job 1 2 3 4 5 Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the order is: Sequence 1 2 3 4 CR 5 Job The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 250. Job 1 2 3 4 5 Date Job Due Received Date 215 220 225 240 250 260 290 300 320 340 Duration (days) 30 20 40 50 20

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Calculate the Critical Ratios​ (CR): ​(Enter all responses rounded to two decimal​ places.)
 
Job
CR
1
enter your response here
Part 2
2
enter your response here
Part 3
3
enter your response here
Part 4
4
enter your response here
Part 5
5
enter your response here
Part 6
Using the Critical Ratio​ (CR) scheduling rule for sequencing the​ jobs, the order​ is:
 
Sequence
Job
1
 
4
5
3
1
2
Part 7
2
 
2
1
5
3
4
Part 8
3
 
5
4
2
3
1
Part 9
4
 
1
3
2
5
4
Part 10
5
 
5
4
1
3
2
 
...
 

Question content area right

Part 1
The following jobs are waiting to be processed at Jeremy​ LaMontagne's machine center. Today is day
250.
                                                                      
Job
Date Job Received
Due Date
Duration​ (days)
1
215
260
30
 
2
220
290
20
 
3
225
300
40
 
4
240
320
50
 
5
250
340
20
 

 

# Critical Ratio (CR) Calculation and Job Sequencing

## Objective
Calculate the Critical Ratios (CR) for the given jobs and determine the sequence using the Critical Ratio scheduling rule. Note that all responses should be rounded to two decimal places.

## Job Information at Jeremy LaMontagne's Machine Center

The following jobs are waiting to be processed:

| Job | Date Job Received | Due Date | Duration (days) |
|-----|-------------------|----------|-----------------|
| 1   | 215               | 260      | 30              |
| 2   | 220               | 290      | 20              |
| 3   | 225               | 300      | 40              |
| 4   | 240               | 320      | 50              |
| 5   | 250               | 340      | 20              |

Today is day 250.

## Critical Ratio Calculation

1. **Formula for Critical Ratio (CR):**
\[ \text{CR} = \frac{\text{Time Remaining}}{\text{Work Remaining}} \]
Where:
\[ \text{Time Remaining} = \text{Due Date} - \text{Current Day} \]
\[ \text{Work Remaining} = \text{Duration (days)} \]

2. **Calculate the CR for each job:**

| Job | Time Remaining | Work Remaining | CR Calculation            | CR   |
|-----|----------------|----------------|----------------------------|------|
| 1   | 260 - 250 = 10 | 30             | CR = 10 / 30               | 0.33 |
| 2   | 290 - 250 = 40 | 20             | CR = 40 / 20               | 2.00 |
| 3   | 300 - 250 = 50 | 40             | CR = 50 / 40               | 1.25 |
| 4   | 320 - 250 = 70 | 50             | CR = 70 / 50               | 1.40 |
| 5   | 340 - 250 = 90 | 20             | CR = 90 / 20               | 4.50 |

3. **CRs Summarized:**

| Job | CR   |
|-----|------|
| 1   | 0.33 |
|
Transcribed Image Text:# Critical Ratio (CR) Calculation and Job Sequencing ## Objective Calculate the Critical Ratios (CR) for the given jobs and determine the sequence using the Critical Ratio scheduling rule. Note that all responses should be rounded to two decimal places. ## Job Information at Jeremy LaMontagne's Machine Center The following jobs are waiting to be processed: | Job | Date Job Received | Due Date | Duration (days) | |-----|-------------------|----------|-----------------| | 1 | 215 | 260 | 30 | | 2 | 220 | 290 | 20 | | 3 | 225 | 300 | 40 | | 4 | 240 | 320 | 50 | | 5 | 250 | 340 | 20 | Today is day 250. ## Critical Ratio Calculation 1. **Formula for Critical Ratio (CR):** \[ \text{CR} = \frac{\text{Time Remaining}}{\text{Work Remaining}} \] Where: \[ \text{Time Remaining} = \text{Due Date} - \text{Current Day} \] \[ \text{Work Remaining} = \text{Duration (days)} \] 2. **Calculate the CR for each job:** | Job | Time Remaining | Work Remaining | CR Calculation | CR | |-----|----------------|----------------|----------------------------|------| | 1 | 260 - 250 = 10 | 30 | CR = 10 / 30 | 0.33 | | 2 | 290 - 250 = 40 | 20 | CR = 40 / 20 | 2.00 | | 3 | 300 - 250 = 50 | 40 | CR = 50 / 40 | 1.25 | | 4 | 320 - 250 = 70 | 50 | CR = 70 / 50 | 1.40 | | 5 | 340 - 250 = 90 | 20 | CR = 90 / 20 | 4.50 | 3. **CRs Summarized:** | Job | CR | |-----|------| | 1 | 0.33 | |
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.