b) Herlich's project manager, Ruby, believes that for the new product to succeed, it must be available for sale before the competitor's product hits the market. Ruby knows that the competitor's product is scheduled to hit the market within 11 weeks from now. Thus, he reckons that Herlich must introduce the new product within 10 weeks and Ruby has also prepared the following information table Find: i. ii. Activity No. of weeks that can be reduced Cost (RM) of each weeks reduced A B C D E 4 2 2 200 150 225 The activities that had their durations reduced and by how many weeks. The new total cost to launch the new product. F 2 175

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

operation research. answer for b

Herlich is planning to launch a new crochet product online. The following table depicts the project
activities that must be completed (in weeks) before the new product can enter the market.
Activity
A
B
C
D
E
F
a) Find:
i.
ii.
iii.
iv.
Description
Research and develop product
Design marketing campaign
Determine crochet patterns
Set up online selling platforms
Set up plant for production
Purchase necessary materials
Predecessors
A
A
B
C
E
The arrow diagram for this project.
The total float and free float for each activity.
The critical path and the project duration.
The total cost for this project.
Duration
4
5
4
3
1
4
Cost (RM)
400
800
520
600
255
600
Transcribed Image Text:Herlich is planning to launch a new crochet product online. The following table depicts the project activities that must be completed (in weeks) before the new product can enter the market. Activity A B C D E F a) Find: i. ii. iii. iv. Description Research and develop product Design marketing campaign Determine crochet patterns Set up online selling platforms Set up plant for production Purchase necessary materials Predecessors A A B C E The arrow diagram for this project. The total float and free float for each activity. The critical path and the project duration. The total cost for this project. Duration 4 5 4 3 1 4 Cost (RM) 400 800 520 600 255 600
b) Herlich's project manager, Ruby, believes that for the new product to succeed, it must
be available for sale before the competitor's product hits the market. Ruby knows that the
competitor's product is scheduled to hit the market within 11 weeks from now. Thus, he
reckons that Herlich must introduce the new product within 10 weeks and Ruby has
also prepared the following information table
Find:
i.
ii.
Activity
No. of weeks that can be reduced
Cost (RM) of each weeks reduced
A
B
C D E
4
2
2
200 150 225
The activities that had their durations reduced and by how many weeks.
The new total cost to launch the new product.
F
2
175
Transcribed Image Text:b) Herlich's project manager, Ruby, believes that for the new product to succeed, it must be available for sale before the competitor's product hits the market. Ruby knows that the competitor's product is scheduled to hit the market within 11 weeks from now. Thus, he reckons that Herlich must introduce the new product within 10 weeks and Ruby has also prepared the following information table Find: i. ii. Activity No. of weeks that can be reduced Cost (RM) of each weeks reduced A B C D E 4 2 2 200 150 225 The activities that had their durations reduced and by how many weeks. The new total cost to launch the new product. F 2 175
Expert Solution
steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.