An urban freeway is to be designed using the following information. AADT = 52,500 veh/day K (proportion of AADT occurring during the peak hour): D (proportion of peak hour traffic traveling in the peak direction): Trucks: PHF = 0.94 Lane width: Shoulder width: Total ramp density: Terrain: free flow speed Determine the number of lanes in the peak direction required to provide LOS C. (Assume commuter traffic and assume no RVs.) 3 ✔lanes Show all calculations required. (Calculate your answers for the peak direction only. Enter fy the peak hour volume in veh/h, the free flow speed in mi/h, the demand flow rate in pc/h/In, the mean speed in mi/h, and the density in pc/mi/In.) fHV 0.893 peak hour volume 6300 Your response differs from the correct answer by more than 10%. Double check your calculations. veh/h 1500 x Your response differs significantly from the correct answer. Rework your solution from the beginning and check each step carefully. mi/h 1900 x Your response differs from the correct answer by more than 10%. Double check your calculations. pc/h/In x mi/h X pc/mi/In demand flow rate mean speed density 0.12 0.65 8% of peak hour volume ✓ 12 ft 10 ft 0.5 interchange/mile; all interchanges are to be cloverleaf interchanges rolling
An urban freeway is to be designed using the following information. AADT = 52,500 veh/day K (proportion of AADT occurring during the peak hour): D (proportion of peak hour traffic traveling in the peak direction): Trucks: PHF = 0.94 Lane width: Shoulder width: Total ramp density: Terrain: free flow speed Determine the number of lanes in the peak direction required to provide LOS C. (Assume commuter traffic and assume no RVs.) 3 ✔lanes Show all calculations required. (Calculate your answers for the peak direction only. Enter fy the peak hour volume in veh/h, the free flow speed in mi/h, the demand flow rate in pc/h/In, the mean speed in mi/h, and the density in pc/mi/In.) fHV 0.893 peak hour volume 6300 Your response differs from the correct answer by more than 10%. Double check your calculations. veh/h 1500 x Your response differs significantly from the correct answer. Rework your solution from the beginning and check each step carefully. mi/h 1900 x Your response differs from the correct answer by more than 10%. Double check your calculations. pc/h/In x mi/h X pc/mi/In demand flow rate mean speed density 0.12 0.65 8% of peak hour volume ✓ 12 ft 10 ft 0.5 interchange/mile; all interchanges are to be cloverleaf interchanges rolling
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![An urban freeway is to be designed using the following information.
AADT = 52,500 veh/day
K (proportion of AADT occurring during the peak hour):
D (proportion of peak hour traffic traveling in the peak direction):
Trucks:
PHF = 0.94
Lane width:
Shoulder width:
Total ramp density:
Terrain:
3
Determine the number of lanes in the peak direction required to provide LOS C. (Assume commuter traffic and assume no RVs.)
lanes.
0.12
0.65
8% of peak hour volume
demand flow rate
12 ft
10 ft
0.5 interchange/mile; all interchanges are to be cloverleaf interchanges
rolling
HV'
Show all calculations required. (Calculate your answers for the peak direction only. Enter fy, the peak hour volume in veh/h, the free flow speed in mi/h, the demand flow rate in pc/h/In, the mean speed in mi/h, and the density in pc/mi/ln.)
fHV
peak hour volume
0.893
free flow speed
mean speed
density
6300
X
Your response differs from the correct answer by more than 10%. Double check your calculations. veh/h
1500
X
Your response differs significantly from the correct answer. Rework your solution from the beginning and check each step carefully. mi/h
1900
X
Your response differs from the correct answer by more than 10%. Double check your calculations. pc/h/In
X mi/h
X pc/mi/In](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Faa0a56ea-6504-40b5-8f5b-02b257b6e155%2Fb8557a6a-f05b-4d0a-bbfd-e257e37bbb0a%2Foxsosn8_processed.png&w=3840&q=75)
Transcribed Image Text:An urban freeway is to be designed using the following information.
AADT = 52,500 veh/day
K (proportion of AADT occurring during the peak hour):
D (proportion of peak hour traffic traveling in the peak direction):
Trucks:
PHF = 0.94
Lane width:
Shoulder width:
Total ramp density:
Terrain:
3
Determine the number of lanes in the peak direction required to provide LOS C. (Assume commuter traffic and assume no RVs.)
lanes.
0.12
0.65
8% of peak hour volume
demand flow rate
12 ft
10 ft
0.5 interchange/mile; all interchanges are to be cloverleaf interchanges
rolling
HV'
Show all calculations required. (Calculate your answers for the peak direction only. Enter fy, the peak hour volume in veh/h, the free flow speed in mi/h, the demand flow rate in pc/h/In, the mean speed in mi/h, and the density in pc/mi/ln.)
fHV
peak hour volume
0.893
free flow speed
mean speed
density
6300
X
Your response differs from the correct answer by more than 10%. Double check your calculations. veh/h
1500
X
Your response differs significantly from the correct answer. Rework your solution from the beginning and check each step carefully. mi/h
1900
X
Your response differs from the correct answer by more than 10%. Double check your calculations. pc/h/In
X mi/h
X pc/mi/In
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning