A local firm manufactures children’s toys. The projected demand over the next fourmonths for one particular model of toy robot isForecasted DemandMonth Workdays (in aggregate units)July 23 3,825August 16 7,245September 20 2,770October 22 4,440 Assume that a normal workday is eight hours. Hiring costs are $350 per workerand firing costs (including severance pay) are $850 per worker. Holding costsare $4.00 per aggregate unit held per month. Assume that it requires an averageof 1 hour and 40 minutes for one worker to assemble one toy. Shortages are notpermitted. Assume that the ending inventory for June was 600 of these toys and themanager wishes to have at least 800 units on hand at the end of October. Assume thatthe current workforce level is 35 workers. Find the optimal plan by formulating as alinear program
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
A local firm manufactures children’s toys. The projected demand over the next four
months for one particular model of toy robot is
Forecasted Demand
Month Workdays (in aggregate units)
July 23 3,825
August 16 7,245
September 20 2,770
October 22 4,440 Assume that a normal workday is eight hours. Hiring costs are $350 per worker
and firing costs (including severance pay) are $850 per worker. Holding costs
are $4.00 per aggregate unit held per month. Assume that it requires an average
of 1 hour and 40 minutes for one worker to assemble one toy. Shortages are not
permitted. Assume that the ending inventory for June was 600 of these toys and the
manager wishes to have at least 800 units on hand at the end of October. Assume that
the current workforce level is 35 workers. Find the optimal plan by formulating as a
linear program