Activity Immediate Optimistic Most Likely Pessimistic
Predecessor Time (a) Time (m) Time (b)
A ____ 2 3 4
B ____ 2 4 6
C A 1 2 3
D B 4 6 9
E C, D 7 8 9
F D 4 7 10
G E 3 4 6
H E, F 7 9 12
a) Construct the project network using excel only