Given the project activity information provided below: a) Draw the project network. b) What are the ES, EF, SL, LS, and LF for each of the nodes in the network? (Given ID, DUR, and Description.) c) What is the critical path? Activity (ID) Description Requirements Architecture 1 2 3 4 5 6 7 8 9 10 11 Design C Design S Design M Coding U Coding T Coding N Integration I Integration J System Preceding Activity None 1 2 2 2 3 4.5 5 6,7 7,8 9,10 Activity Time (DUR) 18 10 15 18 16 8 9 7 8 9 10

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question
Given the project activity information provided below:

a) Draw the project network.

b) What are the ES, EF, SL, LS, and LF for each of the nodes in the network? (Given ID, DUR, and Description.)

c) What is the critical path?

| Activity (ID) | Description     | Preceding Activity | Activity Time (DUR) |
|---------------|-----------------|--------------------|---------------------|
| 1             | Requirements    | None               | 18                  |
| 2             | Architecture    | 1                  | 10                  |
| 3             | Design C        | 2                  | 15                  |
| 4             | Design S        | 2                  | 18                  |
| 5             | Design M        | 2                  | 16                  |
| 6             | Coding U        | 3                  | 8                   |
| 7             | Coding T        | 4,5                | 9                   |
| 8             | Coding N        | 5                  | 7                   |
| 9             | Integration I   | 6,7                | 8                   |
| 10            | Integration J   | 7,8                | 9                   |
| 11            | System          | 9,10               | 10                  |

To analyze the project:

- **ES (Earliest Start)**: The earliest time an activity can start.
- **EF (Earliest Finish)**: The earliest time an activity can finish.
- **SL (Slack)**: The amount of time that an activity can be delayed without causing a delay to subsequent tasks or the project completion date.
- **LS (Latest Start)**: The latest time an activity can start without delaying the project.
- **LF (Latest Finish)**: The latest time an activity can finish without delaying the project.

**Critical Path**: The sequence of activities that determines the shortest time possible to complete the project. Activities on the critical path have zero slack.
Transcribed Image Text:Given the project activity information provided below: a) Draw the project network. b) What are the ES, EF, SL, LS, and LF for each of the nodes in the network? (Given ID, DUR, and Description.) c) What is the critical path? | Activity (ID) | Description | Preceding Activity | Activity Time (DUR) | |---------------|-----------------|--------------------|---------------------| | 1 | Requirements | None | 18 | | 2 | Architecture | 1 | 10 | | 3 | Design C | 2 | 15 | | 4 | Design S | 2 | 18 | | 5 | Design M | 2 | 16 | | 6 | Coding U | 3 | 8 | | 7 | Coding T | 4,5 | 9 | | 8 | Coding N | 5 | 7 | | 9 | Integration I | 6,7 | 8 | | 10 | Integration J | 7,8 | 9 | | 11 | System | 9,10 | 10 | To analyze the project: - **ES (Earliest Start)**: The earliest time an activity can start. - **EF (Earliest Finish)**: The earliest time an activity can finish. - **SL (Slack)**: The amount of time that an activity can be delayed without causing a delay to subsequent tasks or the project completion date. - **LS (Latest Start)**: The latest time an activity can start without delaying the project. - **LF (Latest Finish)**: The latest time an activity can finish without delaying the project. **Critical Path**: The sequence of activities that determines the shortest time possible to complete the project. Activities on the critical path have zero slack.
Expert Solution
steps

Step by step

Solved in 5 steps with 2 images

Blurred answer
Knowledge Booster
Business Analysis Strategies
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education