Predecessors ES EF LS No. weeks Collect requirements 1 -- 2 Analyze Process 3 1 3 Analyze Data 3 4 Design Process 7 5 Design Data 6. 2 Design Screen 1 3, 4 7 Design Reports 4, 5 8 Program 4 6, 7 9. Test and Document 8. 7 10 Install 8, 9 * EL=Early Start, EF-Early Finish, LS=Late Start, LF=Late Finish a. Draw a Network diagram for the activities. b. Calculate Early Start, Early Finish, Late Start and Late Finish for all activities. [Show the calculation in detail] c. Calculate the earliest expected completion time. d. Show the critical path. e. What would happen if activity 6 were revised to take 6 weeks instead of 1 weeks? f. Construct a Gantt chart for the project defined in the Problem. [This Gantt chart has a July 28, 2020 start date.]
Predecessors ES EF LS No. weeks Collect requirements 1 -- 2 Analyze Process 3 1 3 Analyze Data 3 4 Design Process 7 5 Design Data 6. 2 Design Screen 1 3, 4 7 Design Reports 4, 5 8 Program 4 6, 7 9. Test and Document 8. 7 10 Install 8, 9 * EL=Early Start, EF-Early Finish, LS=Late Start, LF=Late Finish a. Draw a Network diagram for the activities. b. Calculate Early Start, Early Finish, Late Start and Late Finish for all activities. [Show the calculation in detail] c. Calculate the earliest expected completion time. d. Show the critical path. e. What would happen if activity 6 were revised to take 6 weeks instead of 1 weeks? f. Construct a Gantt chart for the project defined in the Problem. [This Gantt chart has a July 28, 2020 start date.]
Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
Related questions
Question
5
![Predecessors
ES
EF
No.
weeks
Collect requirements
1
--
2
Analyze Process
3
1
3
Analyze Data
3
4
Design Process
7
2
5
Design Data
2
6.
Design Screen
1
3, 4
7
Design Reports
4, 5
8
Program
4
6, 7
9
Test and Document
8
7
10
Install
8, 9
* EL=Early Start, EF-Early Finish, LS=Late Start, LF=Late Finish
a. Draw a Network diagram for the activities.
b. Calculate Early Start, Early Finish, Late Start and Late Finish for all activities.
[Show the calculation in detail]
c. Calculate the earliest expected completion time.
d. Show the critical path.
e. What would happen if activity 6 were revised to take 6 weeks instead of 1 weeks?
f. Construct a Gantt chart for the project defined in the Problem. [This Gantt chart has a July 28,
2020 start date.]](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F7b3254dd-f467-4b04-8db2-5bdf833d560b%2Ff9dfa990-fe39-42ec-8344-eeab526cf30c%2Ffz9csz_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Predecessors
ES
EF
No.
weeks
Collect requirements
1
--
2
Analyze Process
3
1
3
Analyze Data
3
4
Design Process
7
2
5
Design Data
2
6.
Design Screen
1
3, 4
7
Design Reports
4, 5
8
Program
4
6, 7
9
Test and Document
8
7
10
Install
8, 9
* EL=Early Start, EF-Early Finish, LS=Late Start, LF=Late Finish
a. Draw a Network diagram for the activities.
b. Calculate Early Start, Early Finish, Late Start and Late Finish for all activities.
[Show the calculation in detail]
c. Calculate the earliest expected completion time.
d. Show the critical path.
e. What would happen if activity 6 were revised to take 6 weeks instead of 1 weeks?
f. Construct a Gantt chart for the project defined in the Problem. [This Gantt chart has a July 28,
2020 start date.]
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Recommended textbooks for you

Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education

Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON

Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON

Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education

Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON

Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON

C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON

Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning

Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education