4- As part of a highway interchange project, a ramp will be constructed to allow the vehicles exit the first highway and enter the second highway. The first highway runs north-south and the second one had a right angle to the first one (it runs east-west). Vehicles going to the north can use this exit ramp to enter the second highway as shown in the plan view in the figure below. The design speed in both highways is 100 km/hr. The stationing of the start of the horizontal curve is 40+00. a) Determine the stationing of PI and PT¶ b) The first highway has a vertical grade of +3.5% and the second highway has a grade of - 0.5%. The stationing of the beginning and the end of the crest curve are the same as the horizontal curve. What is the elevation of the end of the vertical curve (PVT) if the elevation of the start point (PVC) is 1500m c) Calculate K for the vertical curve Plan view (horizontal alignment) PT 1 N Profile view (vertical alignment) G1=0.5% PVT PC, 40+00 PVC G1=+3.5%

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter7: Intersection Design
Section: Chapter Questions
Problem 9P
icon
Related questions
Question
100%
4- As part of a highway interchange project, a ramp will be constructed to allow the vehicles
exit the first highway and enter the second highway. The first highway runs north-south and
the second one had a right angle to the first one (it runs east-west). Vehicles going to the
north can use this exit ramp to enter the second highway as shown in the plan view in the
figure below. The design speed in both highways is 100 km/hr. The stationing of the start of
the horizontal curve is 40+00.
a) Determine the stationing of PI and PT¶
b) The first highway has a vertical grade of +3.5% and the second highway has a grade of -
0.5%. The stationing of the beginning and the end of the crest curve are the same as the
horizontal curve. What is the elevation of the end of the vertical curve (PVT) if the
elevation of the start point (PVC) is 1500m
c) Calculate K for the vertical curve
Plan view (horizontal alignment)
PT
1
N
Profile view (vertical alignment)
G1=0.5%
PVT
PC, 40+00
PVC
G1=+3.5%
Transcribed Image Text:4- As part of a highway interchange project, a ramp will be constructed to allow the vehicles exit the first highway and enter the second highway. The first highway runs north-south and the second one had a right angle to the first one (it runs east-west). Vehicles going to the north can use this exit ramp to enter the second highway as shown in the plan view in the figure below. The design speed in both highways is 100 km/hr. The stationing of the start of the horizontal curve is 40+00. a) Determine the stationing of PI and PT¶ b) The first highway has a vertical grade of +3.5% and the second highway has a grade of - 0.5%. The stationing of the beginning and the end of the crest curve are the same as the horizontal curve. What is the elevation of the end of the vertical curve (PVT) if the elevation of the start point (PVC) is 1500m c) Calculate K for the vertical curve Plan view (horizontal alignment) PT 1 N Profile view (vertical alignment) G1=0.5% PVT PC, 40+00 PVC G1=+3.5%
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning